Bridge Special Provisions

Bridge Special Provisions

General

The Bridge Special Provisions, published by the State Bridge Office, may be used by MoDOT's internal staff, as well as consultants, and may be used by other department of transportation agencies as a reference. The Bridge Special Provisions are to be used as an aid to assist in developing Job Specific Special Provisions for statewide bridge related construction projects.


The exclusive purpose of the Bridge Special Provisions is to provide information as a convenience to those who access it. It is the users responsibility to verify the information presented is applicable to their particular project or situation.

Section Title Date
000 Miscellaneous
  Formatting Instructions for Job Special Provisions 08/29/05
  Job Special Provisions Listing 08/17/18
     
102 Bidding Requirements and Conditions
 

Add Alternate Sections JSP-12-03A (See MoDOT internet Job Special Provisions Site)

02/07/18
     
104 Scope of Work
  Construction Requirements 08/11/17
  Stream Gauging Station 01/31/18
  Alternate Structures 04/04/08
  Design of Pre-Engineered Structures for Grade Separation 02/29/08
  Design of Pre-Engineered Structures for Stream Crossings 02/29/08
     
105 Control of Work
  Cooperation Between Contractors 08/29/05
     
206 Dewatering
  Dewatering 10/19/16
     
216 Removals for Bridge Structures
  Match Marking Removal of Bridges 08/29/05
  Major Bridge Removal Specials 08/29/05
  Removal of Cathodic Protection System 08/29/05
  Removal of Exiting Bearings 02/09/18
     
501 Concrete
  Rapid Set Concrete Patching Material - Horizontal Repairs JSP-02-10 (See MoDOT internet  Job Special Provisions Site) 02/01/11
  Rapid Set Concrete Patching Material - Vertical and Overhead Repairs JSP-02-01 (See MoDOT internet Job Special Provisions Site) 02/01/11
     
505 Bridge Deck Concrete Wearing Surface
  Calcium Sulfoaluminate Cement Concrete Wearing Surface 09/04/12
  Surface Sealing Low Slump Concrete 08/29/05
  Polyester Polymer Concrete Overlay 01/10/18
  Steel Fiber Reinforced Concrete Overlay 08/17/18
  Methylmethacrylate Slurry Polymer Concrete Overlay 01/10/18
     
622 Pavement and Bridge Surface Removal and Texturing
  Slurry and Residue Produced During Surface Treatment of PCCP and Bridge Decks JSP-06-05 (See MoDOT internet Job Special Provisions Site) 04/28/06
     
702 Load Bearing Pile
  Static Load Testing 08/29/05
  Dynamic Pile Testing 10/03/13
  Galvanized Structural Steel Pile and Bracing 01/04/17
  Pile Wave Analysis 09/10/13
     
703 Concrete Masonry Construction
  Clearance Gauge 08/29/05
  Cold Weather Concreting 08/29/05
  Form Liners 12/06/16
  Surface Sealing Concrete 08/29/05
     
704 Concrete Masonry Repair
  Deck Girder End Repair 08/29/05
  Epoxy Pressure Injecting 08/29/05
  Half Concrete Filled Steel Grid Deck Repairs 08/29/05
  Clean and Epoxy Seal 02/09/16
  Concrete Wearing Surface Repair 09/16/09
  Total Surface Hydro Demolition with Monolithic Overlay 08/17/18
  Hydro Surface Profiling 07/20/11
  FRP Wrap for Concrete Beams, Piles and Columns 12/06/17
  Shotcrete Concrete Repair 02/02/18
     
705 Prestressed Concrete Members for Bridges
  Post-Tensioned Concrete I-Girders 08/29/05
     
707 Conduit System on Structure
  Cathodic Protection System 08/29/05
  Electrical Grounds 08/29/05
     
711 Protective Coating for Exposed Concrete Surfaces
  Dampproofing 08/29/05
  Waterproofing 08/29/05
  Waterproofing Membrane 08/19/09
  Protective Coatings - Concrete Bents and Piers 11/19/15
  Waterproofing Prestressed Slab Beam Ends 10/30/08
  Water Proofing Membrane - Polyurea 07/16/15
     
712 Structural Steel Construction
  Cleaning, Lubricating and Coating Existing Bearings 09/23/13
  Coating Galvanized Slab Drains 10/25/05
  Drainage System 07/06/15
  Earthquake Restrainers 08/29/05
  Existing Diaphragm Connection to Flange 08/28/13
  Grouting Short Column Jackets 08/29/05
  Non-Destructive Testing 12/15/14
  Pressure Grouting Long Column Jackets 08/29/05
  Rivet Removal and Replacement 08/29/05
  Slab Drain with Grate 07/06/15
  Steel Grid Floor (Half Concrete Filled) 08/29/05
  Strengthening Existing Beams 02/02/18
  Structural Steel Protective Coating Requirements (use w/ no plans) 10/27/14
  Structural Steel Requirements 08/29/05
  Chloride Remediation Process 11/30/15
  Hinge Modification 02/05/14
  Paint Removal 04/24/18
     
716 Neoprene Bearings
  POT Bearings 10/21/10
     
717 Neoprene & Silicone Joint Systems
  Modular Expansion Joint System 08/29/05
     
718 Temporary Bridge
  Superstructure Furnished by the Contractor 08/29/05
     
727 Structural Plate Pipe and Pipe-Arch Culverts
  Pre-Engineered Structural Plate Structures 01/03/08
     
733 Precast Concrete Box Culverts
  Pre-Engineered Precast Concrete Structures 10/31/07
     
1081 Coating of Structural Steel
  Overcoating of Structural Steel (System G) 08/29/05