Counties Impacted
Boone
Route Impacted
70
Work Type
Corridor Upgrades
Planning Phase

Project Summary

As work to update the Environmental Impact Statement wraps up, Improve I-70: Rocheport to Columbia will transition into a Design-Build project. This project is one of several which will modernize the I-70 corridor across the state. Since its original construction more than 50 years ago, I-70 has been a vital lifeline for moving people, goods and information across Missouri and beyond.

Project Goals

  • Deliver the project by December 31, 2029 within the program budget.
  • Provide a third lane of travel for eastbound and westbound I-70 from Rocheport to Columbia.
  • Modernize I-70 while improving pavement, bridges, and interchanges to provide better traffic flow and movement of freight.
  • Minimize construction impacts with a focus on work zone safety, communication, and construction staging while maintaining mobility.
  • Provide expanded employment opportunities while developing and using a diverse workforce

Webform

Sign Up For Improve I-70 News.

Select which e-mail lists you'd like to join. For all Improve I-70 Program updates and monthly reports, select All Improve I-70 News. For project specific press releases, select the project you're interested in. Please note that you may not receive project specific press releases until the selected project begins procurement and/or construction.

*
Choose Your Subscription(s):

Improve I-70: Rocheport to Columbia Milestones

Industry Meeting
MoDOT's Improve I-70 team will host an industry meeting for the Rocheport to Columbia portion of the Improve I-70 Program.

Thursday, May 1, 2025
10 a.m. to Noon
Riechmann Indoor Pavilion
2300 East Walnut Street Columbia, MO 65201

milestone_icon
Release the RFQ
May 1, 2025
milestone_icon
SOQ Due
May 29, 2025
milestone_icon
SOQ Shortlist
June 2025
milestone_icon
Issue the RFP
June 2025
milestone_icon
Proposals Due
November 2025
milestone_icon
Commission Selection of Design-Build Team
December 3, 2025
milestone_icon
Public Meetings
Early 2026
milestone_icon
Construction
Spring/Summer 2026
milestone_icon
Image
Workers on an elevated platform

What is Design-Build?

Design-Build is a delivery method that includes hiring one contracting team to complete the design work and build the highway improvement under one contract. MoDOT provides the project goals, budget and schedule and the contractor team completes the work. This technique has been known to significantly save time and provide cost savings.

Project Contacts

Contact Photo
Photo of Spencer Robinson
Spencer Robinson
Title
Central Project Team Director
Department
Central Office
Contact Photo
Eric Kopinski
Eric Kopinski
Title
Improve I-70 Program Director
Department
Central Office
Contact Info
Contact Photo
Headshot
Lairyn McGregor
Title
Improve I-70 Communications Coordinator
Department
Central Office