PROJECT SUMMARY

MoDOT, in coordination with the Federal Highway Administration, has completed the re-evaluation process to update the Environmental Assessment (EA) of this section of Interstate 70 (I-70). Improve I-70: Boonville to Rocheport is currently in the design process with design consultant, Burns & McDonnell.

This project will add a third lane to I-70 in each direction for the 13-mile section between Missouri Route 5 in Boonville and the Lance Corporal Leon Deraps I-70 Missouri River (Rocheport) Bridge. This project also includes plans to widen two I-70 bridges at MM 113 and 1.2 miles West of the Lance Corporal Leon Deraps I-70 Missouri River (Rocheport) Bridge. The project includes a cost share with the City of Boonville to add a roundabout at the Route B and Americana Dr intersection.  

This project is one of several projects which will widen the I-70 corridor across the state.  MoDOT plans to let this project in January 2026. Construction is currently scheduled to begin in Spring 2026 and is anticipated to be completed late 2028. Since its original construction more than 50 years ago, I-70 has been a vital lifeline for moving people, goods, and information across Missouri and beyond. 

Improve I-70 Program Goals

  • Provide a third lane of travel to eastbound and westbound Interstate 70 from Blue Springs to Wentzville. 

  • Improve the interstate while modernizing the existing pavement and bridges through innovation. 

  • Increase the efficiency of freight movements along Interstate 70. 

  • Minimize construction impacts with a focus on work zone safety, communications, and construction staging. 

  • Expand a diverse workforce through the creation of jobs.

Webform

Sign Up For the Improve I-70 Monthly Newsletter

If you'd like to receive the Improve I-70 Monthly Report via e-mail, please sign up using the form below.

NOTE: This form is for the monthly newsletter. To sign up for project specific press releases, sign up here: MoDOT eUpdate

*

Recent Press Releases

Improve I-70: Boonville to Rocheport

Complete
Environmental Assessment
December 11, 2024
milestone_icon
Complete
Design Consultant Selection
September 2024
milestone_icon
In Progress
Industry Outreach
Summer 2025
milestone_icon
Complete
Public Meeting
Monday, July 21, 2025
4 to 6 p.m.
Boonville High School Gymnasium
1 Pirate Drive Boonville, MO 65233
milestone_icon
Not Started
Letting
January 2026
milestone_icon
Not Started
Ground Breaking
TBD
milestone_icon
Not Started
Construction
Spring 2026 - Late 2028
milestone_icon

Project Contacts

Contact Photo
Eric Kopinski
Eric Kopinski
Title
Improve I-70 Program Director
Department
Central Office
Contact Info
Contact Photo
Headshot
Lairyn McGregor
Title
Improve I-70 Communications Coordinator
Department
Central Office

Related Information

Improve I-70

I-70 is a vital transportation corridor in Missouri, connecting the state’s two largest cities and carrying more rural daily traffic than any other route in the state. The 250 miles of I-70 through Missouri have been an engine for economic growth and...

Improve I-70 Projects

MoDOT has been working on the best plan to be efficient and innovative in how the 200 miles of I-70 will be delivered. As of May 2025, the Improve I-70 individual project limits have been updated and now include eight total project segments across...

Nearby Projects

Improve I-70: Concordia to Boonville

Improve I-70: Concordia to Boonville will be a $541 million Design-Build project that will add a third lane in each direction and improve the 42-mile stretch of Interstate 70 from Route 23 in Concordia to Route 5 in Boonville.

This project is...

Districts Impacted
Central
Kansas City
Counties Impacted
Cooper
Route Impacted
70
Planning Phase

Improve I-70: Rocheport to Columbia

Improve I-70: Rocheport to Columbia is $441 million Design-Build project that will improve the 14-mile stretch of Interstate 70 from the Missouri River Bridge at Rocheport to approximately U.S. Route 63 in Columbia. 

The ESS Team, comprised of...

Districts Impacted
Central
Counties Impacted
Boone
Route Impacted
70
Planning Phase

Improve I-70: Columbia to Kingdom City

Improve I-70 Columbia to Kingdom City is a $426 million Design-Build project. Millstone Weber has been selected as the best-value proposer and Design-Build contractor of Improve I-70: Columbia to Kingdom City. This $405 million fixed-cost contract...

Districts Impacted
Central
Counties Impacted
Callaway
Boone
Route Impacted
70
54
63
In Progress