Counties Impacted
Cole
Route Impacted
50
54
Work Type
Bridge Rehabilitation
Planning Phase

This bundle will address driving surface issues on 11 bridges in Jefferson City, including and deck repairs and overlays, as needed. Included in this project is the removal of a bridge that is no longer in use. Traffic control plans include single-lane closures, narrowing traffic in both directions to one lane, ramp closures, and full road closures.

Embed
Is Responsive
Embed Code

TRAFFIC IMPACTS

Closed bridge over U.S. Route 50 at Route 54 interchange - REMOVAL

During the removal of the trilevel bridge that is no longer in use, U.S. Route 50 and some ramps will be closed for approximately 36 hours. A detour will be signed.

Bolivar Street over U.S. Route 50 – REHABILITATION

This bridge will be closed for roughly 3 months. Additionally, the north sidewalk will be removed along with the portions on either side of the bridge that extend over U.S. Route 50.

U.S. Route 54 over Business Route 50, east and westbound – REHABILITATION

Each bridge will be worked on half at a time, requiring around-the-clock single lane closures. Traffic will be reduced to one lane in each direction, one direction at a time, during construction.

U.S. Route 54 over Linden Drive, east and westbound – REHABILITATION

For the duration of construction, traffic will be reduced to one lane in each direction.

U.S. Route 54 over Stadium Boulevard, east and westbound – REHABILITATION

Each bridge will be worked on half at a time, requiring around-the-clock single lane closures. Traffic will be reduced to one lane in each direction, one direction at a time, during construction.

Madison Street over U.S. Route 54 – REHABILITATION

The bridge from Madison Street onto westbound U.S. Route 54 will be closed for an estimated 37 consecutive day. Motorists will need to use an alternate route.

U.S. Route 54 over Moreau River Drainage, westbound – REHABILITATION

One lane of the bridge will be closed at a time. There will be no impact to eastbound traffic.

U.S. Route 50 over Vetter Lane, east and westbound – REHABILITATION

For the duration of construction, traffic will be reduced to one lane in each direction. There will associated ramp closures as necessary.

PROJECT PROGRESS

In Progress
Planning and Design Phase

The Missouri Department of Transportation and its consultant are designing the rehabilitation of 11 bridges and removal of one bridge that is no longer in use. No additional right of way is needed.

milestone_icon
Complete
Public Input
June 4-18, 2024

During the two-week comment period that ran June 4-18, 2024, the community and interested parties had multiple avenues to learn about, ask questions, and submit input regarding the planned work and associated traffic impacts. 

  1. In person - An open-house style public meeting is being held Tuesday, June 4, 2024, from 4:30 to 6 p.m. at the MoDOT Central District office building, located at 1511 Missouri Boulevard in Jefferson City. The project team will be on hand to answer questions, provide information, and receive input about the project. There will be no formal presentation, so attendees may come and go as they please at any time during the advertised hours.  

  2. Online. All meeting exhibits will be available on this website and feedback will be accepted through the online form below.  

  3. By email – Send your comments to CDCR@modot.mo.gov with the subject line: U.S. Route 50 and U.S. Route 54 Bridge Rehabilitations in Jefferson City Project. 

  4. By traditional mail – Comments may be mailed to Missouri Department of Transportation, 1511 Missouri Boulevard, Jefferson City, MO 65109. Please reference U.S. Route 50 and U.S. Route 54 Bridge Rehabilitations in Jefferson City Project.

milestone_icon
Not Started
Project Letting, Award, and Notice to Proceed

This bundle of bridge work will go out for contractor bids in two separate lettings: U.S. Route 54 in October 2024 and U.S. Route 50 in December 2024.

The Missouri Highways and Transportation Commission may award the U.S. Route 54 contract as part of their November 2024 meeting and the U.S. Route 50 contract as part of their January 2025 meeting. If the contracts are awarded at those meetings, notice to proceed dates will also be given. That is the earliest date the contractor may begin work. 

milestone_icon
Not Started
Project Construction

Construction is expected to take place in 2025, subject to change.

milestone_icon
Webform
Sign Up for Project Updates via Email
*
*