Counties Impacted
Lincoln
Project Status
Planning Phase
Route Impacted
U.S. Route 61
Missouri Route 47

Project Milestones

In Progress
Conceptual design public meeting

(May 2019)

In Progress
Work on preliminary design

(2019 / 2020)

Not Started
Present design at public hearing

(2020)

Construction

(Future - To Be Determined)

  • Construction Expected to Begin Next Week on New Bridge Decks

    02/23/2021

    HANNIBAL – The Missouri Department of Transportation and its contractor, Lehman Construction, LLC, plan to begin work next week, weather permitting, on the U.S. Route 61 northbound bridges between the Warren Barrett Drive and Market Street...

  • Work Begins on Bridges at Taylor Interchange in Marion County

    03/24/2020

    HANNIBAL – Travelers will soon see a lot of activity at the U.S. Routes 61/24 interchange in Marion County near Taylor as preparations begin for rehabilitation work on three bridges at this location.   Last fall, the Missouri Highways and...