Counties Impacted
Boone
Lafayette
Montgomery
Warren
Route Impacted
70
Work Type
Corridor Upgrades
Planning Phase

Project Summary

MoDOT's Improve I-70 Program includes approximately $29 million in INFRA Grant funds to expand availability of truck parking along the I-70 corridor. During peak hours,  all of I-70’s public truck parking areas are over capacity and 75% of truck stops are over capacity. Providing safe off-highway parking reduces the cost of shoulder and guardrail repairs on interstate ramps caused by trucks parking on ramp shoulders and increases safety for all travelers on the road. This project could include improvements at existing truck parking and rest areas in Odessa, Concordia, Boonville, Mineola, and Wright City.

This project will soon transition into a Design-Build project and is one of several which will modernize the I-70 corridor across the state. Since its original construction more than 50 years ago, I-70 has been a vital lifeline for moving people, goods and information across Missouri and beyond.

Project Goals

  1. Deliver the project by December 1, 2028, within the program budget.
  2. Expand and modernize truck parking facilities along I-70 while improving the safety of facilities for users.
  3. Minimize construction impacts with a focus on work zone safety, communication, and construction staging while maintaining mobility.
  4. Provide expanded employment opportunities while developing and using a diverse workforce.

Embed
Is Responsive
Embed Code

Project Milestones

Not Started
Virtual Industry Meeting
January 6, 2026

A virtual industry meeting will be held at 10 a.m. on Tuesday, January 6. A link/phone number to join this meeting will be available beginning Jan. 5.

milestone_icon
Not Started
Issue the RFQ
January 6, 2026
milestone_icon
Not Started
SOQ Due
January 30, 2026
milestone_icon
Not Started
SOQ Shortlist
February 4, 2026
milestone_icon
Not Started
Issue the RFP
February 9, 2026
milestone_icon
Proposals Due
April 17, 2026
milestone_icon
Commission Selection of Design-Build Team
May 6, 2026
milestone_icon

Project Contacts

Contact Photo
Eric Kopinski
Eric Kopinski
Title
Improve I-70 Program Director
Department
Central Office
Contact Info
Contact Photo
Headshot
Lairyn McGregor
Title
Improve I-70 Communications Coordinator
Department
Central Office