Counties Impacted
St. Louis
Route Impacted
115
Work Type
Safety and Operational Improvements
Planning Phase

Project Summary

MoDOT is implementing a project to address the aging pavement and pedestrian facilities along Natural Bridge Rd. (Route 115) from Lucas & Hunt Rd. to the St Louis city limits.  As part of the project, existing sidewalks along the corridor will be upgraded to meet requirements of the Americans with Disabilities Act (ADA).  Constructing new sidewalks will also provide a continuous pedestrian accessible route along the corridor.  

Improvements for this portion of the corridor will include:

  • Pavement resurfacing and new pavement markings 
  • Upgrading the existing sidewalks and curb ramps to meet ADA requirements
  • Replacing several existing entrances to improve the pedestrian walking paths to meet ADA requirements
  • Adding additional midblock crossings and bumpouts (extends the width of the sidewalk and curb line at crosswalks and other locations to keep pedestrians safer)
  • Adding additional lighting for the Pine Lawn area of the corridor
  • Adding Rectangular Rapid Flashing Beacons (RRFBs) 
CONSTRUCTION UPDATE - July 2026

During construction, MoDOT found basements and old coal chutes underneath existing sidewalk, which is to be removed and replaced as part of the project between Rossiter and Francis Avenues. MoDOT inspected these voids underneath the existing sidewalk and the inspections were completed in June 2026.  Because of this unforeseen discovery, the project is being delayed. A public meeting was held on July 7, 2026. For more information, click HERE and on the link below to view information provided during the public meeting.  You may also share your thoughts by completing the comment form by Tuesday, July 21.

CONSTRUCTION UPDATE DISPLAY BOARDS, JULY 2026

COMMENT FORM 

Project Milestones

Complete
Design Phase
Through Fall 2023
milestone_icon
Complete
Public Information Meeting
January 26, 2023, 4-6 p.m.
Pine Lawn City Hall
6250 Steve Marre Ave, 63121

Please see preliminary designs below.

milestone_icon
Complete
Right of Way Acquisitions
Spring 2023
milestone_icon
Complete
Project Advertised
Fall 2023
milestone_icon
Complete
Construction Contract Awarded
Winter 2024
milestone_icon
In Progress
Construction Begins
Spring 2025
milestone_icon
Complete
Public Meeting
Tuesday, July 7, 2026; 4-6 p.m.
Pine Lawn City Hall
6250 Steve Marre Ave. 63121

If you missed the public meeting, you may use the link below to view the informational display boards and share your thoughts on the comment form.  All comments must be received by the close of business on Tuesday, July 21.

CONSTRUCTION UPDATE DISPLAY BOARDS, JULY 2026

FREQUENTLY ASKED QUESTIONS

COMMENT FORM 

milestone_icon
Delayed
Project Completed
September 2026

Due to unforeseen circumstances during construction, the project will be delayed.

milestone_icon

What are the anticipated impacts during construction?

Most of the resurfacing work will take place overnight, with up to two lanes closed. Daytime work will include lane closures and some traffic shifts. Many of the entrances to businesses or subdivisions will be rebuilt.  MoDOT and the contractor will work with residents and businesses to schedule this work and provide least disruption as possible.

Is MoDOT purchasing property from landowners?

MoDOT will need to purchase some property and/or obtain easements in order to construct the additional sidewalks and ADA improvements.  A Right of Way representative will be contacting affected landowners to begin the acquisition process.

Click HERE to view ALL of the project display boards that were shared during the July 7, 2026 public meeting.  The boards provide a construction update on the awarded plans, as well as an alternate concept.  Note:  The alternate concept only covers the Route 115 project from Ridgedale Ave. to St. Louis City limits. After you have viewed the boards, please take a few minutes to share your thoughts on the project by completing the comment form.  Comments must be received by the close of business Tuesday, July 21, 2026.

COMMENT FORM 

CONTACT

Contact Photo
Photo of Tabitha Locke
Tabitha Locke
Title
Area Engineer, North St. Louis County
Department
St. Louis District
Contact Info

Office: 314-453-1749
Email: tabitha.locke@modot.mo.gov 

Contact Photo
Photo of Daniel Savigeau
Daniel Savageau
Title
Project Manager, North St. Louis County
Contact Info

St. Louis District
Phone: 314-453-5089
Email: daniel.savageau@modot.mo.gov