Districts Impacted
Project Summary
The Missouri Department of Transportation, along with its contractor Magruder Paving, will deliver a roadway widening project to improve safety for motorists, and the overall condition and efficiency along 6.7 centerline miles of the Missouri Route 47 corridor between Routes A/D in Hawk Point to just west of Routes H/J in Troy in Lincoln County.
The corridor improvement project will be divided into seven segments that will be constructed over a two-year span with projected completion in 2028. Work will start in Hawk Point to the west and move eastward toward Troy as construction progresses.
Planned improvements will realign two curves in the corridor and allow for the addition of paved shoulders, intersection and profile improvements and pavement resurfacing.
Project Milestones
October 4, 2023
2024
Spring 2026
Contractor: Magruder Paving, LLC
Contract Amt: $18,884,174.74
Monday, July 13, 2026, from 4 p.m. to 6 p.m.
Hawk Point Lions Club Building
180 W. Lincoln Street, Hawk Point, MO
Coming Soon:
Public Meeting Displays & Information
2026 - 2027
Project Information and Public Engagement
Public Hearing - October 4, 2023 | 4 - 6 p.m.
Location: Community Room, Cuivre River Electric Cooperative, 1112 E. Cherry St., Troy, MO
- Informational Handout
- Preliminary Plans
- Section 106 Environmental Display
- Map of Project Limits
- Typical View of Roadway Display
Public Informational Meeting - July 13, 2026 | 4 - 6 p.m.
Location: Hawk Point Lions Club Building, 180 W. Lincoln St., Hawk Point, MO
Coming Soon:
Public Meeting Displays & Information
News Releases
-
Construction Begins on Missouri Route 47 Widening Project in Lincoln County
HANNIBAL – The Missouri Department of Transportation, along with its contractor Magruder Paving, will begin a roadway widening project to improve safety for motorists, and the overall condition and efficiency of the Missouri Route 47 corridor between...
-
Public Meeting to be Held for Missouri Route 47 Widening Project from Hawk Point to Troy
HANNIBAL – The public is invited to an informational meeting to share project information regarding construction phases, traffic control plans and planned detour routes for the Missouri Route 47 roadway widening project, located between Routes A/D in...
-
Utility Work Continues in Preparation for Missouri Route 47 Widening Project in Lincoln County
HANNIBAL – Waterline utility work is scheduled to begin as early as June 22 along Missouri Route 47 between Lincoln Trail and Bohemian Church Road near Hawk Point in Lincoln County, weather permitting. Traffic will not be impacted during this phase...
-
Public Hearing Scheduled for Route 47 Improvements in Lincoln County
HANNIB AL – The Missouri Department of Transportation (MoDOT) will host a public hearing from 4:00 to 6:00 p.m. on Wednesday, October 4 at Cuivre River Electric Cooperative, 1112 E. Cherry St., Troy, Missouri 63379.
The open house style hearing will...
2023 Public Hearing - Materials/Displays
2026 Public Informational Meeting - Materials/Displays
Frequently Asked Questions
How much does the project cost?
Approximately $18-20 million
What are the anticipated impacts?
Construction details have not been finalized at this time. MoDOT will work with residents and business owners to ensure access is available during construction.
Will the road be closed during construction?
Customers can anticipate temporary traffic impacts throughout the project. A few full closures of Route 47 will be necessary to complete the improvements. MoDOT will make every reasonable effort to minimize the closure time during construction. More information regarding traffic impacts will be shared through news releases and social media for each stage of construction as details become available.
Will MoDOT need to acquire any right of way?
Yes. In 2024, MoDOT's Right of Way staff and consultants will beginning the process of contacting property owners for any necessary right of way needed for the project. Right of way discussions are anticipated to continue through Fall 2025.
How can I stay updated about the project?
Stay updated on news about roadwork in your area by signing up for emails at eUpdates at MoDOT.org
Who can I contact if I have further questions?
Questions about the project may be directed to Keith Killen, MoDOT's project manager overseeing the project at keith.killen@modot.mo.gov or Jeff Niemeyer, Area Engineer, at jeffrey.niemeyer@modot.mo.gov
Project Contacts
Keith Killen, P.E.
Title
Assistant District Engineer
Department
Northeast District
Contact Info
Jeff Niemeyer
Title
Area Engineer
Department
Northeast District
Contact Info
Email: jeffrey.niemeyer@modot.mo.gov
Phone: (573) 808-3562
Email: jeffrey.niemeyer@modot.mo.gov
Phone: (573) 808-3562