Counties Impacted
St. Louis
Route Impacted
367
Work Type
Safety and Operational Improvements
Planning Phase

Project Summary

MoDOT is performing a Traffic Safety & Operations study for the Route 367 corridor, from just south of I-270 to just north of the Halls Ferry Circle. Engineers will review safety, speed, and crash data for the corridor, as well as review current and projected traffic volumes based on anticipated growth in the area.

Two public meetings will be held in spring and summer 2024. The first public meeting will be to gather public input and communicate initial data-gathering efforts to date, both of which will inform the ongoing traffic study and formulation of alternatives. The second public meeting will discuss traffic study findings, present alternatives that were studied, and share the preferred alternative planned for more detailed evaluation.

ROUTE 367 FACT SHEET

Project Milestones

In Progress
Study Begins
January 2024
milestone_icon
In Progress
Public Engagemant
February - March 2024
  • Stakeholder Listening Sessions
milestone_icon
Public Meeting #1
Spring 2024
  • Present current data analysis
  • Gather public input to form alternatives
  • Launch public survey
milestone_icon
Data Collection and Analysis
Spring - Summer 2024
  • Traffic study
  • Formulate alternatives
milestone_icon
Public Engagement
April - May 2024
  • Promote survey
milestone_icon
Public Meeting #2
Summer 2024
  • Share traffic study findings
  • Present alternatives considered
  • Present preferred alternative
milestone_icon
Initital Study Ends, Design to Follow
Summer 2024
milestone_icon

How can the public help?

There are multiple opportunities for public engagement on this project.

  1. Listening sessions will be held with key organizations contacted by the project team.
  2. Attend our two public meetings. Dates and details will be posted on this website.
  3. Complete the public survey. A link will be shared on this website and will go live with the first public meeting.
  4. Comments are always welcome and encouraged! Leaders of the project team are listed below. Emails are encouraged, and please reference the Route 367 Traffic Study.

What happens next?

The Traffic Safety & Operations study is expected to be completed summer 2024. Design of the planned improvements is expected to be completed by December 2026.

What will be the impact to traffic?

The project is currently in the study and analysis phase.  Periodic traffic data collection will be performed, but no construction will take place at this time, and traffic will not be interrupted.

How much will the project cost?

Up to $4 million in safety funds are anticipated to be used for safety improvements on the corridor.

WHO TO CONTACT

Contact Photo
Photo of Tabitha Locke
Tabitha Locke
Title
Area Engineer, North St. Louis County
Department
St. Louis District
Contact Info

Office:  (314) 453-1749
Email:  Tabitha.Locke@modot.mo.gov

Contact Photo
Headshot of Jamie Rana, Transportation Project Manager in the MoDOT St. Louis District
Jamie Rana
Title
Transportation Project Manager
Department
St. Louis District
Contact Info

Phone: 314-624-5035

Email:  Jamie.Rana@modot.mo.gov