11-Month Closure FAQ's
When does the closure begin and how long will it last?
The closure begins in early-January 2027, and is scheduled through mid-December 2027 (approximately 11 months), weather and unforeseen circumstances permitting.
What are the official detour routes for local and metro-area traffic?
Due to the project area size, there will not be a singular detour route to accommodate all of the traffic for this closure. MoDOT encourages motorists to plan alternative routes in advance and choose the detour that best meets their
individual travel needs. MoDOT will maintain access to many of the cross streets for local traffic to navigate the area during the closure. Signed detour routes will be designated for city street closures. Metro-area traffic is encouraged to utilize the highway system throughout Kansas City to navigate the closure. This includes I-435, I-35, I-29, I-635, US-71, or other alternate routes. I-435 and I-35 will be signed. For those traveling to and from the downtown Kansas City area to the Truman Sports Complex area, use I-35 and I-435 to the north or US-71 and I-435 to the south.
What is the detour route for regional I-70 trough traffic?
MoDOT will detour regional travelers passing through the Kansas City area on I-70 to use I-435 and I-470 to loop south of the closure. Travelers on the Missouri and Kansas sides will be directed to this route using Kansas City Scout’s overhead message boards.
Why does the interstate have to close completely?
A complete closure allows the work to be completed significantly faster than if the work was done under typical staged construction. A full closure also maximizes safety for motorists, pedestrians and workers, and minimizes overall long-term inconvenience to motorists and the local community.
What improvements are being made during the 11 months?
Work taking place during the closure will include construction of a fourth eastbound thru-lane on I-70 between The Paseo and Van Brunt Blvd., replacement of the mainline bridges, reconstruction of the Benton and Jackson curves, and additional related improvements on this section of I-70.
Will it be closed in both directions or just one?
I-70 will be completely closed in both directions between The Paseo and Van Brunt Blvd.
Exactly which section of I-70 is closing?
I-70 east of downtown Kansas City will be closed between The Paseo and Van Brunt Blvd. There will be a multi-week period during Summer 2026 where the Manchester Trfy exit will be the eastern limit of the project. MoDOT will maintain access to most of the cross streets for local traffic to navigate the area during the closure. Signed detour routes will be designated for city street closures.
How will daily commuters get downtown?
MoDOT will maintain access to many of the cross streets for local traffic to navigate the area during the closure. Commuters should allow for extra travel time, consider adjusting departure times, use real-time navigation, and determine the best route depending on the origin and destination, as well as current traffic conditions.
How will game day traffic (Chiefs/Royals) work?
MoDOT recommends that fan traffic between downtown Kansas City and the Truman Sports Complex avoid the central I-70 corridor entirely during the 11-month closure.
From downtown KC to the Stadiums:
Drivers are encouraged to use I-35 North to I-435 South, or US-71 South to I-435 North.
From the Stadiums back to downtown:
Drivers can utilize I-435 North to I-35 South, or I-435 South to US-71 North.
Stadium directional signs will be updated to guide game day traffic along these designated regional loops.
Will trucks divert through neighborhoods?
Regional truck traffic will be directed to remain on the interstate system rather than use neighborhood streets as a detour. This includes I-435, I-35, I-29, I-635, US-71, or other alternate routes. I-435 and I-35 will be signed. MoDOT will detour regional travelers passing through the KC area on I-70 to use I-435 and I-470 to loop south of the closure. Travelers on the Missouri and Kansas side will be directed to this route using Kansas City Scout’s overhead message boards.
How will emergency responders and school buses navigate the closure?
MoDOT is coordinating with the Kansas City Police Department, Kansas City Fire Department, local hospitals, schools, and other agencies in advance of the closure to maintain critical access and establish appropriate routes.
How will RideKC bus routes be affected?
Several RideKC routes that currently use I-70 or cross street bridges will be rerouted to detour routes. Closer to the closure date, updated bus schedules and detours can be found online at the Ride KC website https://ridekc.org.
Will local businesses and neighborhoods remain accessible?
Businesses will remain open and both businesses and neighborhoods will be accessible.
How is the Improve I-70 KC project coordinating this closure with the closure of I-670 for Roy Blunt Luminary Park?
For closure notifications and project information related to Luminary Park, visit the project website at http://luminarypark.org.
General Project FAQs
Why is this project necessary?
This project will help to improve reliability, safety, infrastructure, and community connectivity.
- Reliability - consistency of travel for motorists and pedestrians will continue to worsen without much needed changes to the corridor.
- Safety - crashes, involving motorists and pedestrians, will continue to increase without safety improvements.
- Infrastructure – the corridor infrastructure, including bridges, pavement, barrier, and drainage has reached the end of its service life, and needs to be replaced, rehabilitated, or upgraded. Without infrastructure upgrades, planned and emergency lane closures for maintenance and repairs will only increase, adding to further delay for motorists.
- Community Connectivity - improving pedestrian and bicycle facilities is a must and upgrades are needed immediately to better serve the public.
What is the project's budget?
The budget of the Improve I-70 KC project is $237 million.
Will the project impact travel during the World Cup?
During the FIFA World Cup events in June and July of 2026, the contractor-team has committed to keeping three thru lanes of I-70 open to traffic in each direction, to help accommodate the many out-of-town visitors expected for that event. Any ongoing work along I-70 and the city crossroads will be minimized.
How will the project improve pedestrian/bicycle access?
Existing pedestrian facilities within the project along city crossroads where bridges are replaced, will be updated to meet ADA standards and accommodate the KC Bike Plan. The project will add local roadway and pedestrian connections along the corridor.
What is being done about the "Benton Curve" and the "Jackson Curve"?
The curves near Benton Blvd. and Jackson Ave. will be reconstructed and brought up to current design standards. The changes will allow traffic to safely travel at the posted 55mph speed limit.
Why is so much brush being removed along the corridor?
Brush and trees are being cleared (March 2025) along the corridor in preparation for the rest of the Improve I-70 KC project. The clearing is taking place in areas that will require grading and in areas where utility work will be taking place as part of the project.
Why doesn't the project include construction of a fourth westbound lane?
The Improve I-70 KC project will construct a fourth eastbound thru lane from Prospect Ave. to the bridge over Manchester Tfwy and the Blue River. A fourth westbound thru lane is not being constructed with this project at this time due to the capacity limitations west of the project in the downtown loop. The increased capacity of a fourth westbound thru lane would increase the traffic delays east of the downtown loop – particularly during the morning rush hour period. Until funding and plans are in place to make improvements to the downtown loop area, there is no overall benefit to adding an additional fourth westbound thru lane at this time.
Although this project will not include an additional westbound lane, the new bridges and walls being constructed within this project are being built with space to allow for the construction of a fourth westbound lane in the future.
Is this project part of the Statewide Improve I-70 Program?
No. While this project is funded separately from the Statewide Improve I-70 Program, which will add a third lane in each direction of I-70 between Blue Springs and Wentzville, the Improve I-70 Kansas City project is one of several projects that will modernize the I-70 corridor across the state.
What is Design-Build?
Design-build is a delivery method that includes hiring one contracting team to complete the design work and build the highway improvement under one contract. MoDOT provides the project goals, budget and schedule and the contractor team completes the work. This technique has been known to significantly save time and provide cost savings.