Design-Build Information

Download the MoDOT Design-Build flyer by clicking here.

General

As per Sec. 227.107, RSMo, MoDOT was given the authority for three pilot projects using the design-build project delivery technique: The New I-64, kcICON and the Safe & Sound Bridge Improvement Program. Each was completed ahead of schedule and on, or under, budget.

Subsequently, the statute was amended to give MoDOT the opportunity to enter into design-build contracts on no more than two percent of the total number of all state highway system projects awarded to contracts for construction from projects listed in the commission’s approved statewide transportation improvement project for that state fiscal year.

Design-build is a delivery method that includes hiring one contracting team to complete the design work and build the highway improvement under one contract. MoDOT provides the project goals, budget and schedule and the contractor team completes the work. This technique has been known to significantly save time and provide cost savings.

Image
hands at computer

Alternative Project Delivery Webinar

MoDOT has been working with AGCMO and ACECMO to improve communication on Design-Build and other Alternative Project Delivery methods and to look for opportunities to strengthen the program.

As part of that effort, MoDOT hosted a webinar on June 30, 2020, featuring a 30-minute presentation from a panel including MoDOT’s Dave Simmons, Don Rosenbarger of Delta Companies and Bruce Wylie from ACECMO.

View the Webinar

Design-Build Projects in Procurement

 

February 21, 2020 - For immediate release

 

Design-Build Teams Selected to Compete for Bootheel Bridge Bundle Project

SIKESTON - The Missouri Department of Transportation has received Statements of Qualification from potential design-build teams for the Bootheel Bridge Bundle project, which will repair or replace 15 bridges on the Southeast District’s asset management plan.

The SOQs have been evaluated and four teams have been prequalified to proceed.

“We are excited about the interest we have received in the project. Four teams have been selected to compete for the contract to oversee the design and construction of this bridge bundle project,” said MoDOT Project Director Jessie Philpot.


The following teams were selected to further develop their proposals on the project:

  • Kiewit - Benesch
  • Lehman - Wilson
  • Robertson Contractors, Inc.
  • Kozeny – Wagner, Inc.

Design-build projects combine both the design and construction phases into one contract. The selected contract team completes the design and construction in parallel instead of in succession, which saves time and resources.

Thirteen bridges in the Bootheel Bridge Bundle are included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state and was authorized by the Missouri General Assembly in the 2019 legislative session.

MoDOT will issue the Request for Proposal this March. The design-build team is expected to be selected in July 2020, with construction beginning as early as summer 2020.

 

Thank you to everyone who expressed interest and put in the time and effort to deliver a SOQ for consideration,” Philpot added.

 

For more information on the Bootheel Bridge Bundle, please visit the project webpage available at: https://www.modot.org/bootheel-bridge-bundle.

 

Procurement Schedule

Release Request for Qualifications                Jan. 13, 2020

Statement of Qualifications Due                    Feb. 11, 2020

Release Request for Proposals                       March 2020

Technical Discussions                                      March-June 2020

Final Technical Proposals & Price                   July 2020

Allocation Due

MHTC Selection of Best-Value Proposer        August 2020

Notice to Proceed #1                                      September 2020

 

Project Goals

  1. Deliver the project within the program budget of $25.2 million on or before Dec. 31, 2023.
  2. Use innovation to maximize the number of locations to be addressed while providing quality structures sensitive to location and traffic.
  3. Minimize public inconvenience through increased construction speed and flexibility in scheduling.
  4. Improve safety at each location.

This design-build project will replace the U.S. Route 169 Buck O’Neil Bridge over the Missouri River in Kansas City. More information can be found in the federal BUILD Grant application, or by contacting Project Director Mary Miller at mary.miller@modot.mo.gov, or 816-607-2030.

Request for Design-Build Services Letters of Interest for the U.S. Route 169 Bridge over the Missouri River

The Missouri Department of Transportation (MoDOT) is soliciting Letters of Interest from companies interested in providing design-build services for the John Jordan “Buck” O’Neil Memorial Bridge(formerly the Broadway Bridge), that carries U.S. Route 169 over the Missouri River and connects downtown Kansas City with communities north of the river in Jackson and Platte Counties.

MoDOT intends to replace the 100-year-old existing Buck O’Neil Bridge and make improvements to the U.S. Route 169 corridor. The anticipated improvements include replacing the existing Missouri River bridge, improving traffic operations, geometrics, and safety and bike/pedestrian/transit accessibility along U.S. Route 169, including direct connections from I-35 to U.S. Route 169. One design-build team will be selected to design and construct the project. In addition to design and construction, other project elements such as right-of-way acquisition, quality management and environmental management may be included as part of the design-build contract.

A virtual information presentation is scheduled at 10 a.m., Tuesday, July 21, 2020. A link to the meeting will be available on the project website, www.modot.org/buck-oneil-bridge-project  It is anticipated the Request for Qualifications will be released on the same day as the presentation.

Firms interested in receiving project information should send a one-page Letter of Interest to MoDOT by registered mail or similar delivery method that indicates proof of receipt, no later than Wednesday, July 15, 2020, to ensure that you receive all information. The Letters of Interest will allow MoDOT to compile a list of interested companies for notices and any announcements relating to the project.

Address all letters to:

Mary Miller, P.E
Project Director
Missouri Department of Transportation
600 N.E. Colbern Road, Lees Summit, MO 64086

 

The draft RFQ for the Buck O’Neil Bridge design-build project is available for informational purposes only.  It is anticipated that the final RFQ will be released after the industry meeting on July 21, 2020.   Please send any comments on the Draft RFQ to BuckONeilBridge@modot.mo.gov.   No clarifications on details of the draft RFQ will be answered at this time. 

Draft Project Goals:

  1. Construct an innovative, low-maintenance Missouri River Bridge that will provide a century of service within the program budget
  2. Provide a safe, connective and accessible transportation facility that improves regional and local system performance
  3. Manage the impact to the travelling public during construction 
  4. Complete the project by December 1, 2024, utilizing a diverse workforce 

Updated Draft Procurement Schedule (May 29, 2020): 

Due to the COVID-19 pandemic, the procurement schedule for the Buck O’Neil Bridge design-build project has been revised. The RFQ/Industry meeting has been moved to July; the RFP release is still scheduled for August and the award is currently still set for February 2021. Moving the RFQ release to July allows for a better picture of MoDOT’s revenue going forward due to COVID-19 impacts. The schedule below is tentative based on those revenue projections.

Project Advertisement:            July 6, 2020

RFQ/Industry meeting:             July 21, 2020

SOQ shortlist:                               August 2020

RFP:                                                 August 2020

Award:                                            February 2021

The Central District Americans with Disabilities Act project will bring specific ADA pedestrian facilities located throughout the district into compliance to the maximum extent feasible in accordance with MoDOT Standards and the Public Right of Way Accessibility Guidelines.  For more information, Project Director Chris Brownell at sidney.brownell@modot.mo.gov, or (573) 526-4567.

 

Mid MO ADA Project Status Update – Project Postponed

The Mid MO ADA (Americans with Disabilities Act) project has been postponed until further notice. Due to the April 6 release of the Request for Qualifications (RFQ) and Industry Meeting, this message is being provided to alert contractors and consultants of the postponement. 

The purpose of the Mid MO ADA Design-Build project is to complete the current ADA Transition plan in the Central District by bringing the remaining locations into ADA compliance. The procurement process began with project advertisement on February 28, and the RFQ was released on April 6.  The Statement of Qualifications (SOQ) was due to be received on May 1, prior to the project being postponed.

More details pertaining to the Mid MO ADA postponement will be provided soon.

 

Project Goals:

1. Deliver the project within the program budget of $13.6 million.

2. Bring designated pedestrian facilities into ADA compliance.

3. Use innovation to maximize improvements that provide a long-lasting and safe pedestrian facility.

4. Safely deliver a project that minimizes and mitigates construction impacts through construction staging and communication efforts.

5. Complete the project no later than December 1, 2022.

Upcoming Design-Build Projects

 

I-70 Missouri River Bridge at Rocheport

MoDOT will soon begin the procurement process for a Design-Build project to replace the I-70 Missouri River Bridge at Rocheport. A re-evaluation of the Environmental Assessment that was completed in 2005 in this vicinity is currently underway, with expected completion this winter.

Though tentative, procurement is expected to begin in early 2021. For more information, contact the project team at RocheportBridge@modot.mo.gov

 

 

 

Fixing Access to Rural Missouri (FARM) Bridge Program

This $26 million design-build project will replace up to 41 bridges in northern Missouri, and was enabled by receipt of a $20.7 million federal grant under the Competitive Highway Bridge Program. MoDOT’s original application for the grant which contains the project information can be found here.The project schedule will be determined once more information is available, but MoDOT does not anticipate starting the procurement process until late 2020. For more information, contact Project Director Jeff Gander at FARM@modot.mo.gov.

Solicitation for Owner Engineer: https://www.modot.org/modot-solicitations-rfq

 

 

I-70 Corridor in St. Charles County 

This project will make crossroad, interchange and outer road improvements to I-70 in St. Charles County, between Fairgrounds and Cave Springs Roads, to make the corridor safer and more reliable. For more information, contact Project Director Stacey Smith at 314-453-5084, or by email at anastasia.smith@modot.mo.gov

DRAFT GOALS:
1.    Maximize improvements within the program budget. 
2.    Improve safety, reliability, and efficiency of the transportation network allowing for future expansion. 
3.    Improve connectivity to surrounding neighborhoods and businesses. 
4.    Provide a durable and maintainable transportation infrastructure. 
5.    Minimize impacts to the traveling public during construction while safely delivering the project by November 1, 2023. 
6.    Deliver the project using a diverse workforce.
 

Projects with Scoping Only

 

The purpose of this section is to identify potential future highway and bridge projects. These projects may be in the evaluation stage, which is called project scoping, or may be further along in the preliminary design process. Projects listed in this section are not commitments to construct or implement an improvement. These commitments won’t be made until the NEPA process is completed. These projects are being included in the STIP for the scoping or preliminary design phase only, and subsequent phases have not yet been determined or are beyond the STIP horizon period.

For more information on MoDOT Design-Build projects, please contact Dave Simmons at 314-453-1878, or at David.J.Simmons@modot.mo.gov

 

  • Missouri Route 740 (Central District) – No information available
  • I-44 Gasconade and Little Piney River (Central District) – No information available
  • Safety Improvements (Northwest District) – No information available
  • I-70/Route 131 Interchange at Odessa (Kansas City District) – No information available
  • I-70 Corridor Improvements (Kansas City District) – No information available
  • I-70 Realignment at Wentzville (St. Louis District) – No information available
  • Kansas City ADA Project (Kansas City District) – No information available
  • Safety Improvements (St. Louis District) – No information available
  • I-44 Bridge Bundle (Southwest District) – No information available

Projects Underway

Mineola Hill Climbing Lanes Design-Build Project

This highway project was made possible by a federal Infrastructure for Rebuilding America (INFRA) grant in combination with the replacement of the I-70 Missouri River Bridge at Rocheport in Boone and ...

I-270 North Project

The I-270 North Design-Build Project seeks to improve reliability within the I-270 corridor, link communities, and enhance traffic operations so that the public has a durable and maintainable transpor...

I-44 Project Bridge Rebuild

On Feb. 6, 2019, the Missouri Highways and Transportation Commission selected the Emery Sapp & Sons/Parsons Transportation Group team as the design-build contractor for I-44 Project Bridge Rebuild...

Completed Design-Build Projects

U.S. Route 54 “Champ Clark Bridge” over the Mississippi River – Pike County

On June 29, 2017, the Missouri Highways and Transportation Commission selected the Massman/HNTB team to design and construct a new Champ Clark Bridge at Louisiana, Mo. The existing narrow two-lane bri...

I-435 South Loop Link - Jackson County

On Dec. 1, 2017, the Missouri Highways & Transportation Commission selected the Radmacher-Wilson Team – construction contractor Radmacher Brothers Excavating Inc. and the engineering design firm o...

St. Louis Safety Project – Franklin and St. Charles counties

In May 2017, the Missouri Highways and Transportation Commission selected the NB West Contracting Company to improve safety at 31 locations in Franklin and St. Charles counties. Other members of the t...

U.S. Route 69 Bridges – Kansas City

In July 2014, the Missouri Highways and Transportation Commission selected the American Bridge Company and Garver team as the design-build contractor for the U.S. Route 69 Bridges project. The $79 mil...

Interstate 44/Route 141 – St. Louis County

In January 2016, the Missouri Highways and Transportation Commission selected the Pace Construction team, including AECOM Technical Services, Kuesel Excavating Company and the Lochmueller Group, as th...

I-64 Daniel Boone Bridge over the Missouri River – St. Charles/St. Louis counti…

In July 2012, the Missouri Highways and Transportation Commission selected the Walsh-Alberici joint venture team as the design-build contractor for the new I-64 Daniel Boone Bridge. The $125 million ...

Route 364 Upgrade - Phase 3 – St. Charles County

In February 2013, the Missouri Highways and Transportation Commission selected the Page Constructors Joint Venture, including Fred Weber Inc., Millstone-Bangert Inc., Kolb Grading with lead designer P...

I-70 Bridges over Manchester Trafficway – Kansas City

In July 2013, The Missouri Highways and Transportation Commission selected the Clarkson Construction Company and HNTB team as the design-build contractor for the Manchester Bridge Project. MoDOT repl...

The New I-64

This project – the largest, single highway construction project in MoDOT history – involved rebuilding 10 miles of Interstate 64 from west of Spoede Road in St. Louis County to Kingshighway Boulevard ...

kcICON

The kcICON design-build project improved 4.7 miles of Interstate 29/35 in Kansas City from just north of Route 210 (Armour Road) to the northeast corner of the downtown Kansas City, MO. Freeway loop. ...

Safe and Sound Bridge Improvement Program

More than 800 of Missouri’s worst bridges were repaired or replaced under the Safe and Sound Bridge Improvement Program, which was completed in October 2012 – under its $685 million budget and 14 mont...

Project Freeway: U.S. 60 Rogersville

In June 2014, the Missouri Highways and Transportation Commission selected the Ozark Regional Road Constructors, including Radmacher Brothers Excavating Company; Reynolds, Smith & Hills; CFS Engin...

Columbia I-70 Bridges – Boone County

In June 2015, the Missouri Highways and Transportation Commission selected Emery Sapp and Sons and the Parsons Transportation Group as the design-build contractor for the Columbia I-70 Bridges project...