Design-Build Information

Download the MoDOT Design-Build flyer by clicking here.

General

As per Sec. 227.107, RSMo, MoDOT was given the authority for three pilot projects using the design-build project delivery technique: The New I-64, kcICON and the Safe & Sound Bridge Improvement Program. Each was completed ahead of schedule and on, or under, budget.

Subsequently, the statute was amended to give MoDOT the opportunity to enter into design-build contracts on no more than two percent of the total number of all state highway system projects awarded to contracts for construction from projects listed in the commission’s approved statewide transportation improvement project for that state fiscal year.

Design-build is a delivery method that includes hiring one contracting team to complete the design work and build the highway improvement under one contract. MoDOT provides the project goals, budget and schedule and the contractor team completes the work. This technique has been known to significantly save time and provide cost savings.

Image
hands at computer

MoDOT’s Upcoming Design-Build Projects

MoDOT conducted a webinar on Nov. 10, 2020, to discuss upcoming design-build projects.  Click the button below to watch the event recording.

Watch the Recorded Webinar

 

 

Design-Build Projects in Procurement

 

Aug. 14, 2020 – For immediate release        

MoDOT Takes the Next Step to Building a New Buck O’Neil Bridge

JACKSON/CLAY COUNTIES After an extensive and exhaustive evaluation process, the Missouri Department of Transportation has developed a list of qualified design-build teams to compete for the contract to build a new U.S. Route 169 Buck O’Neil Bridge. Each of the teams come from a diverse mix of experienced local and national companies who submitted exceptional proposals.

“We are excited about the interest we have received in the project. Five teams have been selected to compete for the contract to oversee the design and construction of this bridge project,” said MoDOT Project Director Mary Miller.

The following teams (in no particular order) were selected to further develop their proposals on the project:

  • American Bridge/Parsons Team
  • Lunda Construction Co.
  • Massman-Clarkson, a joint venture
  • Traylor Ames Joint Venture
  • The Walsh Design-Build Team

Design-build projects combine both the design and construction phases into one contract. The selected contract team completes the design and construction in parallel instead of in succession, which saves time and resources.

From this group, the Missouri Highways and Transportation Commission will select a best-value proposal from a design-build team to deliver the project. The selection is expected in February 2021, with construction beginning later that year.

The John Jordan “Buck” O’Neil Memorial Bridge (formerly the Broadway Bridge), is a triple arch bridge carrying U.S. 169 over the Missouri River, and serves as a key regional connection between downtown Kansas City and communities north of the river.

While safe, the bridge is nearing the end of its projected lifespan. Opened in 1956, the bridge recently celebrated its 60th year of operation. 

Since that time, neighborhoods and communities on both sides of the bridge have changed significantly and now nearly 50,000 vehicles use the bridge daily.

“Thank you to everyone who expressed interest and put in the time and effort to deliver a SOQ for consideration,” Miller added.

For more information on the U.S. Route 169 Buck O’Neil Bridge, please visit the project webpage available at: https://www.modot.org/buck-oneil-bridge-project

Project Goals:

  1. Construct an innovative, low-maintenance Missouri River Bridge that will provide a century of service within the program budget of $247.5 million.
  2. Provide a safe, connective and accessible transportation facility that improves regional and local system performance.
  3. Manage the impact to the travelling public during construction. 
  4. Complete the project by December 1, 2024, utilizing a diverse workforce.

 

Procurement Schedule
Project Advertisement July 6, 2020
RFQ/Industry Meeting July 21, 2020
SOQ Shortlist August 17, 2020
RFP August 31, 2020
Award February 2021

This $26 million design-build project will replace up to 41 bridges in northern Missouri, and was enabled by receipt of a $20.7 million federal grant under the Competitive Highway Bridge Program. MoDOT’s original application for the grant which contains the project information can be found here. For more information, contact Project Director Jeff Gander at FARM@modot.mo.gov.

Solicitation for Owner Engineer: https://www.modot.org/modot-solicitations-rfq

REQUEST FOR LETTERS OF INTEREST FOR DESIGN-BUILD SERVICES

The Missouri Department of Transportation (MoDOT) is soliciting Letters of Interest from companies interested in providing design-build services for the FARM Bridge Program in the Northeast and Northwest Districts.

The project’s primary purpose is to replace up to 41 deficient bridges across these two districts. These bridges are located on low-volume routes and are:

  • Weight-restricted
  • In poor condition
  • On timber pile
  • One-lane but carry two-way traffic

One design-build team will be selected to design and construct the project. MoDOT will use a best-value selection process to evaluate the ability of the design-build proposers to meet or exceed the following project goals:

  1. Safely deliver the project within the program budget of $21.98 million on or before October 31, 2023.
  2. Use innovation to maximize the number of locations to be addressed.
  3. Provide quality long-lasting structures.
  4. Minimize public inconvenience through increased construction speed and flexibility in scheduling.

A virtual information presentation is scheduled from 1 p.m. to 4 p.m., Monday, Nov. 16, 2020.  A link to the meeting will be available on the project website, www.modot.org/farm-bridge-program.  It is anticipated the Request for Qualifications (RFQ) will be released on the same day as the presentation.

Firms interested in receiving FARM Bridge Program Design-Build information should send a one-page Letter of Interest to MoDOT by registered mail, or similar delivery method that indicates proof of receipt, no later than Monday, Nov. 9, 2020, to ensure that you receive all information. The Letters of Interest will allow MoDOT to compile a list of interested companies for notices and any announcements relating to the FARM Bridge Program Design-Build Project.

Address all letters to:

Jeffery L. Gander, P.E.

FARM Bridge Program Design-Build Project

Missouri Department of Transportation

1711 South Highway 61

Hannibal, MO 63401

Include in your Letter of Interest the company name and a contact person at your company including, address, phone and e-mail. If your firm is a Disadvantaged Business Enterprise (DBE), indicate with which local or state agencies you are certified.

 

PROJECT GOALS:

  1. Safely deliver the project within the program budget of $21.98 million on or before Oct. 31, 2023.
  2. Use innovation to maximize the number of locations to be addressed.
  3. Provide quality long-lasting structures.
  4. Minimize public inconvenience through increased construction speed and flexibility in scheduling.

PROJECT SCHEDULE:

PROCUREMENT SCHEDULE

Project Advertisement

October 15, 2020

 

Industry Meeting/RFQ Release

November 16, 2020

 

SOQ’s Due

December 14, 2020

 

SOQ Shortlist

December 23, 2020

 

RFP Release

January 12, 2021

 

One-on-One Technical Meetings

January through March

 

Proposals Due

April 6, 2021

 

Award at MHTC Meeting

May 2021

 

This project will make crossroad, interchange and outer road improvements to I-70 in St. Charles County, between Fairgrounds and Cave Springs Roads, to make the corridor safer and more efficient. For more information, contact Project Director Stacey Smith at 314-453-5084 or by email at anastasia.smith@modot.mo.gov or visit the project website at www.i70csfg.com

 

I-70 CSFG Industry Meeting

 

 

Event address for attendees:

https://modot.webex.com/modot/onstage/g.php?MTID=eb523729ff4094d4c793178bd1db2c8ea

Date and time:

Monday, Dec. 7, 2020 1:00 pm
Central Standard Time

Duration:

2 hours

Description:

The I-70 Cave Springs to Fairground Design-Build Project Team will provide a brief presentation to industry attendees.

Audio conference:

To receive a call back, provide your phone number when you join the event, or call the number below and enter the access code.

Call-in toll number (US/Canada)

1-408-792-6300

Show all global call-in numbers

Access code: 132 979 7771

 

PROJECT GOALS:

  1. Maximize improvements within the program budget of $62 million.
  2. Improve safety and efficiency of the transportation network while supporting connectivity for the local community.
  3. Provide a durable and maintainable transportation infrastructure allowing for future expansion.
  4. Minimize impacts to the traveling public during construction while safely delivering the project by November 1, 2023.
  5. Deliver the project using a diverse workforce.

 

PROJECT SCHEDULE:

PROCUREMENT SCHEDULE

Project Advertisement

November 2, 2020

Industry Meeting/RFQ Release

December 7, 2020

SOQ Shortlist

January 18, 2021

RFP Release

February 5, 2021

Award at MHTC Meeting

June 2021

Upcoming Design-Build Projects

 

I-70 Missouri River Bridge at Rocheport

MoDOT will soon begin the procurement process for a Design-Build project to replace the I-70 Missouri River Bridge at Rocheport. Though tentative, procurement is expected to begin in early 2021. A re-evaluation of the 2005 Environmental Assessment in this vicinity was completed earlier this year.

Early Release Information for the I-70 Missouri River Bridge at Rocheport is Now Available

In anticipation of procurement in early 2021, MoDOT has prepared some Early Release Information for all consultants and contractors interested in pursuing the design-build contract. Any consultant or contractor may request access to this information by emailing RocheportBridge@modot.mo.gov or Project Director Brandi Baldwin at  brandi.baldwin@modot.mo.gov.

 

Project Schedule

Issue RFQ & Industry Meeting                                    January 29, 2021

SOQs Due                                                                            February 2021

Shortlist announced                                                       March 2021

Issue RFP                                                                             March 2021

Proposals due                                                                    June 2021

MHTC award                                                                      July 2021

Open to traffic                                                                   August 2024

Project complete                                                             December 2024

 

Project Goals:
 

  • Meet the expectation of delivering the project under budget.
  • Provide a high quality, durable, low maintenance project that improves safety and reliability.
  • Minimize traffic impacts during and after construction while maximizing safety and capacity.
  • Maximize safety for workers while beating the project completion deadline of 12/31/24.
  • Deliver the Project with a diverse workforce that fosters future DBE and workforce development.
  • Demonstrate a commitment to quality and innovation in all phases of the project.

 

The Central District Americans with Disabilities Act project will bring specific ADA pedestrian facilities located throughout the district into compliance to the maximum extent feasible in accordance with MoDOT Standards and the Public Right of Way Accessibility Guidelines.  For more information, Project Director Chris Brownell at sidney.brownell@modot.mo.gov, or (573) 526-4567.

 

Mid MO ADA Project Status Update

The Mid MO ADA Design-Build Project was postponed in April of this year due to anticipated loss of MoDOT’s fuel tax revenue as a result of the national shutdown of businesses surrounding the national pandemic.  MoDOT was tasked by the US DOT to keep our STIP projects moving forward as planned.  This project was moved out to a later fiscal year to help alleviate Central District revenue losses in the short term.  Currently, the Mid MO ADA Project has been placed in the first quarter of fiscal year 2022 and Central District is committed to maintain this award date.  Team meetings are again underway and the project is moving forward to a project advertisement later in 2020 or early 2021.  As the project progresses and more details are ready to be shared, they will be posted on the project website at https://www.modot.org/midmoada

 

Project Goals:

1. Deliver the project within the program budget of $13.6 million.

2. Bring designated pedestrian facilities into ADA compliance.

3. Use innovation to maximize improvements that provide a long-lasting and safe pedestrian facility.

4. Safely deliver a project that minimizes and mitigates construction impacts through construction staging and communication efforts.

5. Complete the project no later than December 1, 2022.

 

 

 

Projects with Scoping Only

 

The purpose of this section is to identify potential future highway and bridge projects. These projects may be in the evaluation stage, which is called project scoping, or may be further along in the preliminary design process. Projects listed in this section are not commitments to construct or implement an improvement. These commitments won’t be made until the NEPA process is completed. These projects are being included in the STIP for the scoping or preliminary design phase only, and subsequent phases have not yet been determined or are beyond the STIP horizon period.

For more information on MoDOT Design-Build projects, please contact Dave Simmons at 314-453-1878, or at David.J.Simmons@modot.mo.gov

 

  • Missouri Route 740 (Central District) – No information available
  • I-44 Gasconade and Little Piney River (Central District) – No information available
  • Safety Improvements (Northwest District) – No information available
  • I-70/Route 131 Interchange at Odessa (Kansas City District) – No information available
  • I-70 Corridor Improvements (Kansas City District) – No information available
  • I-70 Realignment at Wentzville (St. Louis District) – No information available
  • Kansas City ADA Project (Kansas City District) – No information available
  • Safety Improvements (St. Louis District) – No information available
  • I-44 Bridge Bundle (Southwest District) – No information available

Projects Underway

Mineola Hill Climbing Lanes Design-Build Project

This highway project was made possible by a federal Infrastructure for Rebuilding America (INFRA) grant in combination with the replacement of the I-70 Missouri River Bridge at Rocheport in Boone and ...

I-270 North Project

The I-270 North Design-Build Project seeks to improve reliability within the I-270 corridor, link communities, and enhance traffic operations so that the public has a durable and maintainable transpor...

I-44 Project Bridge Rebuild

On Feb. 6, 2019, the Missouri Highways and Transportation Commission selected the Emery Sapp & Sons/Parsons Transportation Group team as the design-build contractor for I-44 Project Bridge Rebuild...

Bootheel Bridge Bundle Project

“The purpose of the Bootheel Bridge Bundle project is to repair or replace 15 bridges on the Missouri Department of Transportation’s asset management plan for the Southeast District,” said Project Dir...

Completed Design-Build Projects

U.S. Route 54 “Champ Clark Bridge” over the Mississippi River – Pike County

On June 29, 2017, the Missouri Highways and Transportation Commission selected the Massman/HNTB team to design and construct a new Champ Clark Bridge at Louisiana, Mo. The existing narrow two-lane bri...

I-435 South Loop Link - Jackson County

On Dec. 1, 2017, the Missouri Highways & Transportation Commission selected the Radmacher-Wilson Team – construction contractor Radmacher Brothers Excavating Inc. and the engineering design firm o...

St. Louis Safety Project – Franklin and St. Charles counties

In May 2017, the Missouri Highways and Transportation Commission selected the NB West Contracting Company to improve safety at 31 locations in Franklin and St. Charles counties. Other members of the t...

U.S. Route 69 Bridges – Kansas City

In July 2014, the Missouri Highways and Transportation Commission selected the American Bridge Company and Garver team as the design-build contractor for the U.S. Route 69 Bridges project. The $79 mil...

Interstate 44/Route 141 – St. Louis County

In January 2016, the Missouri Highways and Transportation Commission selected the Pace Construction team, including AECOM Technical Services, Kuesel Excavating Company and the Lochmueller Group, as th...

I-64 Daniel Boone Bridge over the Missouri River – St. Charles/St. Louis counti…

In July 2012, the Missouri Highways and Transportation Commission selected the Walsh-Alberici joint venture team as the design-build contractor for the new I-64 Daniel Boone Bridge. The $125 million ...

Route 364 Upgrade - Phase 3 – St. Charles County

In February 2013, the Missouri Highways and Transportation Commission selected the Page Constructors Joint Venture, including Fred Weber Inc., Millstone-Bangert Inc., Kolb Grading with lead designer P...

I-70 Bridges over Manchester Trafficway – Kansas City

In July 2013, The Missouri Highways and Transportation Commission selected the Clarkson Construction Company and HNTB team as the design-build contractor for the Manchester Bridge Project. MoDOT repl...

The New I-64

This project – the largest, single highway construction project in MoDOT history – involved rebuilding 10 miles of Interstate 64 from west of Spoede Road in St. Louis County to Kingshighway Boulevard ...

kcICON

The kcICON design-build project improved 4.7 miles of Interstate 29/35 in Kansas City from just north of Route 210 (Armour Road) to the northeast corner of the downtown Kansas City, MO. Freeway loop. ...

Safe and Sound Bridge Improvement Program

More than 800 of Missouri’s worst bridges were repaired or replaced under the Safe and Sound Bridge Improvement Program, which was completed in October 2012 – under its $685 million budget and 14 mont...

Project Freeway: U.S. 60 Rogersville

In June 2014, the Missouri Highways and Transportation Commission selected the Ozark Regional Road Constructors, including Radmacher Brothers Excavating Company; Reynolds, Smith & Hills; CFS Engin...

Columbia I-70 Bridges – Boone County

In June 2015, the Missouri Highways and Transportation Commission selected Emery Sapp and Sons and the Parsons Transportation Group as the design-build contractor for the Columbia I-70 Bridges project...