Project locations are organized by phase. Within each phase, projects are ordered from west to east.
Panel Color Key:
- Blue -- Not Started
- Red -- Under Construction
- Green -- Construction Complete
PHASE 1 (2025)
23rd St. over I-70
Description: Bridge replacement and upgraded pedestrian facilities on 23rd St. over I-70
Status: Open
Latest News: NOW OPEN: 23rd St. bridge over I-70, Dec. 11 | Missouri Department of Transportation
25th St. Pedestrian Bridge
Description: New pedestrian bridge over I-70 at 25th St.
Status: Open
Latest News: NOW OPEN: New 25th St. pedestrian bridge over I-70 | Missouri Department of Transportation
PHASE 2 (2026)
I-70 at Benton Blvd ("Benton Curve")
Description: Reconstruction of I-70 at Benton Blvd ("Benton Curve") to bring it up to current design standards.
Status: Under Construction
Traffic Impacts:
- Benton Ave. CLOSED between Truman Rd. and 13th St. until Summer 2027. The I-70 WB on-ramp will remain open for Benton Ave. southbound travelers. Detour: use 13th St. Indiana Ave. and Truman Rd.
- Intermittent lane closures on I-70
Estimated Completion: Fall 2027
Cleveland Ave. over I-70
Description: Bridge replacement and upgraded pedestrian facilities on Cleveland Ave. over I-70
Status: Not started; closing for replacement on Feb. 9, 2026.
Traffic Impacts:
- Full closure of Cleveland Ave. over I-70
- Intermittent lane/ramp closures on I-70
- MOTORIST DETOUR: utilize 23rd St., Indiana Ave., and 27th St.
- PEDESTRIAN DETOUR: utilize 24th St. Ter., the 25th St. pedestrian bridge, Askew Ave., 26th St., Monroe Ave., and 27th St.
Estimated Completion: December 2026
27th St. over I-70
Description: Bridge replacement and upgraded pedestrian facilities on 27th St. over I-70
Status: Closed
Traffic Impacts:
- Full closure of 27th St. over I-70
- Ramps closed from I-70 EB to 27th St. and from 27th St. to I-70 WB
- Intermittent lane closures on I-70
- DETOUR: utilize Cleveland Ave., 31st St., and Jackson Ave.
Estimated Completion: Fall 2026
I-70 at Jackson Ave. ("Jackson Curve")
Description: Reconstruction of I-70 at Jackson Ave. ("Jackson Curve") to bring it up to current design standards
Status: Under Construction
Traffic Impacts:
- Jackson Ave. CLOSED between I-70 on- and off-ramps. Detour: use 27th St., Cleveland Ave., and 31st. St.
- Ramp from I-70 EB to 31st St. (Exit 5B) permanently closed
Estimated Completion: Fall 2027
Lister Ave. over I-70
Description: Bridge replacement and upgraded pedestrian facilities on Lister Ave. over I-70
Status: Closed since Nov. 3, 2025; demolition occurred on Nov. 7-10, 2025
Traffic Impacts:
- Full closure of Lister Ave. over I-70
- Intermittent lane/ramp closures on I-70
Estimated Completion: 2026
Oakley Ave. Pedestrian Bridge
Description: Pedestrian bridge replacement near Oakley Ave. over I-70
Status: Closure began on Nov. 7, 2025; demolition occurred on Nov. 7-10, 2025
Traffic Impacts:
- Full closure of pedestrian bridge. Pedestrian detour: provided at Van Brunt Ave.
- Intermittent lane closures on I-70
- PEDESTRIAN DETOUR: utilize 29th Ter., Van Brunt Blvd, and 30th Ter.
Estimated Completion: 2026