Counties Impacted
Jackson
Route Impacted
70
Work Type
Environmental Impact Study
Planning Phase

Improve I-70 KC

The Kansas City District of the Missouri Department of Transportation (MoDOT), in coordination with the Federal Highway Administration (FHWA), is improving Interstate 70 (I-70) between The Paseo Boulevard and U.S. 40/31st Street, also known as Improve I-70 KC. The project will be administered using the design-build delivery method.

The re-evaluation of the Second Tier Environmental Impact Statement and the conceptual Access Justification Report have been approved by FHWA. MoDOT has also approved right-of-way plans for the corridor to begin early acquisition of key parcels.

While this project is funded separately from the Statewide Improve I-70 Program, which will add a third lane in each direction of I-70 between Blue Springs and Wentzville, Improve I-70 KC is one of several projects that will modernize the I-70 corridor across the state.  Since its original construction more than 50 years ago, I-70 has been a vital lifeline for moving people, goods and information across Missouri and beyond.

Improve I-70 KC Goals

  • Deliver the project within the programmed budget of $223 million by December 31, 2028.
  • Implement innovative transportation solutions to improve safety and reliability along the corridor.
  • Provide durable and maintainable infrastructure that revives the corridor and aligns with regional development.
  • Improve accessibility for the local community and create opportunities to grow a diverse workforce.
  • Minimize overall traffic impact during construction in partnership with stakeholders.

Additional Resources

Check out the most up-to-date fact sheet for more information about Improve I-70 KC.

Stay in the Know - Current Press Releases

Embed
Improve I-70 KC
Is Responsive
Embed Code

Project Milestones

Complete
EIS Re-evaluation
milestone_icon
Complete
Public Meeting #1

March 2022

milestone_icon
Complete
Public Meeting #2

September 2022

milestone_icon
Complete
Request for Letters of Interest

June 2023

milestone_icon
Complete
Industry Meeting

July 27, 2023

Presentation   |   Sign In Sheet Q&A
 

milestone_icon
Complete
Issue Draft RFQ

July 27, 2023

Draft RFQ   |   Forms

milestone_icon
Complete
Industry Meeting

February 13, 2024

Presentation | Sign In Sheet | Q&A

milestone_icon
Complete
Issue RFQ
milestone_icon
Complete
SOQ Shortlist

April 10, 2024

The pre-qualified teams are as follows:

  • Clarkson-Radmacher Joint Venture: Clarkson Construction Company and Radmacher Brothers Excavating Company with HNTB Corporation
  • Lunda Team: Lunda Construction Company with Parsons
milestone_icon
Complete
Issue RFP

April 15, 2024

milestone_icon
Not Started
Commission Selection of Design-Build Team

August 7, 2024

milestone_icon
Not Started
Construction

Fall/Winter 2024

milestone_icon
Image
Workers on an elevated platform

What is Design-Build?

Design-build is a delivery method that includes hiring one contracting team to complete the design work and build the highway improvement under one contract. MoDOT provides the project goals, budget and schedule and the contractor team completes the work. This technique has been known to significantly save time and provide cost savings.