Potential Design-Build Projects

The purpose of this section is to identify potential future highway and bridge projects that are being considered for Alternative Delivery. Projects listed in this section have not been Approved for Alternative Delivery the anticipated schedule may change. State Fiscal Year runs from July 1 to June 30. THESE DATES ARE SUBJECT TO CHANGE.

Project List

Improve I-70 Logo Project Page
I-70 Improvements Missouri River to Route 67 - St. Louis

Owner Consultant Services – Acquired. Status – Potential Procurement RFP Fiscal Year 2026

Improve I-70 Logo Project Page
I-70 Bridge over MO 40 - Kansas City

Owner Consultant Services - TBD Status – Potential Procurement RFP Fiscal Year 2027

Interstate 44 Improvements - Southwest

I-44 Between U.S. 65 and Missouri Route 13. Owner Consultant Services – Acquired. Status – Potential Procurement RFP Fiscal Year 2025

Missouri Highway 47 Road Sign
MO 47 Improvements - St. Louis

Owner Consultant Services – Acquired Status – Potential Procurement RFP Fiscal Year 2027

Improve I-70 Logo Project Page
Improve I-70: Rocheport to Columbia

Project to improve Interstate 70 from Rocheport to Columbia. The award of this project is currently scheduled for Spring 2026 and could be completed by the end of 2029.

Improve I-70 Logo Project Page
Improve I-70: Kingdom City to Warrenton

Project to improve Interstate 70 from Kingdom City to Warrenton. The award of this contract is currently scheduled for Spring 2027 and could be completed by Summer 2030.

Improve I-70 Logo Project Page
Improve I-70: Odessa to Boonville

Project to improve Interstate 70 from Odessa to Boonville. The award of this project is schedule for late 2027 and could be completed by the end of 2030.

Forward 44: Southwest District

Missouri’s FY2024 budget from the General Assembly signed into law by Gov. Parson provided $20 million of General Revenue for an environmental study more than 250 miles of the I-44 corridor from the O...

Forward 44: Central District

Missouri’s FY2024 budget from the General Assembly signed into law by Gov. Parson provided $20 million of General Revenue for an environmental study more than 250 miles of the I-44 corridor from the O...

Missouri Route 291 Missouri River Bridge

MO 291 Missouri River Bridges – Kansas City Owner Consultant Services – Acquired Status – Potential Procurement RFP Fiscal Year 2026

Improve I-70 STL Conceptual Study

The Missouri Department of Transportation is conducting a conceptual study to identify potential improvements for two adjacent sections of I-70 between the Missouri River and North Hanley Road.