Boone/Callaway County U.S. Route 63 Bridge Rehabilitation Project Milestones
Complete
Boone County Route AC (Grindstone Parkway) Bridge Over U.S. Route 63
June-September 2019
Complete
U.S. Route 63 Northbound Bridge over Bonne Femme Creek
July-August 2019
Complete
U.S. Route 63 Northbound Bridge over Gans Creek
September-October 2019
Complete
U.S. Route 63 Northbound Bridge over Katy Trail
September-October 2019
Complete
U.S. Route 63 Northbound Bridge over Turkey Creek
October-November 2019
Complete
U.S. Route 63 Southbound Bridge over Gans Creek
October-November 2019
Complete
U.S. Route 63 Southbound Bridge over Cedar Creek
March-May 2020
Why was this work necessary?
The rehabilitation and preventive maintenance extends the life of the bridges.
When did the work take place?
The project was awarded in the spring of 2019, with construction between the summer of 2019 and the spring of 2020.
What did the project cost?
The total cost is approximately $3.9 million.
News Releases
- Route 63 Bridge Improvements Begin Monday at Grindstone Parkway
- Informational Meeting to Discuss Work on Route AC Bridge in Columbia
- Route 63 Bridge at Bonne Femme Creek to Close for Rehabilitation
- Route AC Bridge Over Route 63 is Now Open
- Final Phase of Route 63 Bridge Improvement Project Rescheduled to Begin March 30
- Final Phase of Route 63 Bridge Rehabilitation Project to Take Place Monday