U.S. ROUTE 54 PAVEMENT IMPROVEMENTS IN CALLAWAY COUNTY
U.S. Route 54 from the Missouri River Bridge to north of Interstate 70 in Callaway County will have a new driving surface soon. Construction crews will remove the existing surface layer and replace with new pavement. Guardrail will also be replaced and upgraded, where needed.
PROJECT PROGRESS
The Missouri Department of Transportation designed pavement and guardrail improvements on U.S. Route 54 from Missouri River Bridge to north of I-70.
The Missouri Highways and Transportation Commission awarded a $24,463,380.36 contract to Magruder Paving, LLC to complete this project and three others (U.S. Route 54 eastbound expansion, rehabilitation work on three bridges over U.S. Route 54 in Callaway County, and intersection improvements at U.S. Route 54 and Old Jefferson City Road).
In preparation for resurfacing, construction crews began making pavement repairs on July 22. This work will require nightly lane closures from 7 p.m. to 6 a.m. All work is weather-permitting, and schedules are subject to change.
Resurfacing it expected to get underway in mid-August.
Work will require temporary lane closures and possibly some temporary narrowed lanes. U.S. Route 54 will remain open through the duration of the project. The contractor will be required to work at night on certain segments of U.S. Route 54, both for the safety of the crews and to lessen traffic impacts.
Work is expected to be completed by May 22, 2025.
Project updates
-
Nightly lane closures begin tonight on U.S. Route 54 north of the Missouri River
JEFFERSON CITY, Mo. – In preparation for resurfacing, construction crews will begin pavement repairs on U.S. Route 54 in Callaway County. This work will require nightly lane closures from 7 p.m. to 6 a.m. starting tonight. All work is weather...
-
Overpass work to impact ramps at Route 54, Route 63, Route 94 interchange beginning July 15
JEFFERSON CITY, Mo. – Rehabilitation work on the U.S. Route 63/Missouri Route 94 overpass bridges over U.S. Route 54 is set to begin next week. Starting July 15, Magruder Paving, LLC, working with the Missouri Department of Transportation, will...
FREQUENTLY ASKED QUESTIONS
Why is MoDOT resurfacing U.S. Route 54 north of Jefferson City?
All road surfaces become worn over time and it becomes necessary to lay new pavement. This will improve the drivability and safety for motorists.
How will the work affect traffic?
U.S. Route 54 will remain open through the duration of the project. The contractor will be required to work at night on certain segments of U.S. Route 54, both for the safety of the crews and to lessen traffic impacts.
Who can I contact with further questions?
You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference U.S. Route 54 Pavement Improvements in Callaway on your inquiries.
How can I stay updated on the project’s progress?
Sign up for project-specific updates using the form below.
![Image of the various projects along U.S. Route 54 in North Jefferson City.](http://dpv85fgkqesen.cloudfront.net/sites/default/files/styles/feature_block/public/2023-10/U.S.%20Route%2054%20Project%20Map.jpg?itok=m1poWKQ2)
PROJECT COORDINATION
Other improvements to U.S. Route 54 in the vicinity include widening the eastbound traveled way, intersection improvements, washing the bridges over the Missouri River, and rehabilitation work on several bridges (north and south of the Missouri River).