U.S. Route 54/Old Jefferson City Road Intersection Improvements in Callaway County

The addition of acceleration and deceleration lanes, installation of offset left turn lanes, and removal of the crossover on U.S. Route 54 at the intersection with Old Jefferson City Road/County Road 306 will help improve safety and traffic flow.

Project Milestones

Complete
Planning, Design and Right of Way Acquisition phase.

The Missouri Department of Transportation and their consultants designed intersection improvements that include:

  • Installing offset left-turn lanes at Old Jefferson City Road/County Road 306.
  • Pavement widening of U.S. Route 54 for the addition of acceleration and deceleration lanes.
  • Removal of the crossover at the intersection.

The estimated cost for these improvements as of May 30, 2023, is $1.6 million. This cost may change.

milestone_icon
Complete
Public Input
Comment period: June 29 - July 14, 2023

Public Meeting

An open-house style public informational meeting was held Thursday, June 29, 4:30 to 6 p.m. at the Fulton City Council Chambers. Fulton City Hall is located at 18 East 4th Street, Fulton, MO. Attendees were able to come and go as they please from 4:30 to 6 p.m., as there was no formal presentation. Members of the project team were there to answer questions and provide information. Exhibits were available showing the work currently being planned at the intersection.

 

Attendees were able to leave comments with the project team, either verbally or written. Written comments were also accepted by mail, postmarked on or before July 14, to: 

Callaway County U.S. Route 54/Old Jefferson City Road Intersection Project, 1511 Missouri Boulevard, Jefferson City, MO 65102

 

Meeting Exhibits

At the link below, find all exhibits presented at the in-person meeting. Comments were also accepted via an online form (active June 29 - July 14).

milestone_icon
Complete
Contract Letting, Award & Notice to Proceed

The Missouri Highways and Transportation Commission awarded the contract for this work to Magruder Paving, LLC.

milestone_icon
Not Started
Project Construction, Traffic Impacts and Completion

At this time, construction is anticipated in 2024.

The roadway is expected to remain open during construction with single-lane closures during working hours under traffic control.

milestone_icon

Q: Why is MoDOT changing these intersections?

A: The addition of acceleration and deceleration lanes, installing offset left-turn lanes at Old Jefferson City Road, and removing the crossover at the intersection will help improve safety and traffic flow.

 

Q: Will U.S. Route 54, Old Jefferson City Road or County Road 306 be closed during construction?

A: At this time, the roadway is expected to remain open, but motorists will encounter lane closures throughout the construction process.

 

Q: Who can I contact if I have further questions?

A: Questions about the project may be directed to MoDOT's Customer Service team at CDCR@modot.mo.gov or by phone at 888 ASK MODOT (1-888-275-6636). Please refer to the Callaway County Intersection Improvement Project at U.S. Route 54 and Old Jefferson City Road in emails or by phone to ensure your questions are directed to the correct personnel.

 

Q: How can I stay updated on the project's progress?

A: Keep visiting this page, follow MoDOT's Central District on social media, sign up for email/text alerts at Modot.org, or use the form below to sign up for project-specific updates. 

  • MoDOT to hold public meeting in Fulton