Counties Impacted
Greene
Project Status
Planning Phase
Route Impacted
U.S. Route 60
Missouri Route 174

Project Facts:

  • Relocate eastbound lanes closer to westbound lanes in Route 60 median at Route 174
  • Consolidate two intersections at Route 60/Route 174 into one intersection
  • Install new traffic signals
  • Build new sidewalks in areas (City of Republic contributing money toward sidewalks.)
  • Estimated total project cost: $2 million
  • Construction: July 2020-May 2021

Traffic Impacts:

  • Much of work will take place in Route 60 median at Route 174
  • Nighttime lane closings on Route 60 and on Route 174
  • Crews and equipment close to traffic

News Releases/Project Updates

  • Resurfacing/Intersection Projects on U.S. 60/Missouri Route 413

    06/25/2020

    Republic Area, Greene County – Drivers can expect nighttime lane closings on U.S. Route 60/Missouri Route 413 between Springfield and Republic along with median work at the intersection of Route 60/413 and Missouri Route 174 beginning the week of...