Districts Impacted
U.S. ROUTE 54 PAVEMENT IMPROVEMENTS IN CALLAWAY COUNTY
U.S. Route 54 from the Missouri River Bridge to north of Interstate 70 in Callaway County will have a new driving surface soon. Construction crews will remove the existing surface layer and replace with new pavement. Guardrail will also be replaced and upgraded, where needed.
PROJECT PROGRESS
The Missouri Department of Transportation designed pavement and guardrail improvements on U.S. Route 54 from Missouri River Bridge to north of I-70.
The Missouri Highways and Transportation Commission awarded a $24,463,380.36 contract to Magruder Paving, LLC to complete this project and three others (U.S. Route 54 eastbound expansion, rehabilitation work on three bridges over U.S. Route 54 in Callaway County, and intersection improvements at U.S. Route 54 and Old Jefferson City Road).
Construction crews began with pavement repairs on July 22, 2024, and resurfacing U.S. Route 54 in Callaway County started Aug. 12, 2024. Work is being paused through the winter months and will resume in the spring of 2025.
This work requires temporary lane closures and possibly some temporary narrowed lanes. U.S. Route 54 will remain open throughout the duration of the project. The contractor is required to work at night on certain segments of U.S. Route 54, both for the safety of the crews and to lessen traffic impacts.
Work is expected to be completed by May 22, 2025.
Project updates
-
Ramp from westbound U.S. Route 54 to northbound U.S. Route 63 to close Tuesday night
JEFFERSON CITY, Mo. – The ramp from westbound U.S. Route 54 to northbound U.S. Route 63 is scheduled to close overnight Tuesday. Construction crews working with the Missouri Department of Transportation plan close the ramp from 7 p.m. April 8 through...
-
Resurfacing U.S. Route 54 in Callaway County to pick back up next week
JEFFERSON CITY, Mo. – The resurfacing project that began in summer 2024 on U.S. Route 54 in Callaway County is set to resume next week.
After the winter hiatus, construction crews working with the Missouri Department of Transportation will pick...
FREQUENTLY ASKED QUESTIONS
Why is MoDOT resurfacing U.S. Route 54 north of Jefferson City?
All road surfaces become worn over time and it becomes necessary to lay new pavement. This will improve the drivability and safety for motorists.
How will the work affect traffic?
U.S. Route 54 will remain open through the duration of the project. The contractor will be required to work at night on certain segments of U.S. Route 54, both for the safety of the crews and to lessen traffic impacts.
Who can I contact with further questions?
You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference U.S. Route 54 Pavement Improvements in Callaway on your inquiries.
How can I stay updated on the project’s progress?
Sign up for project-specific updates using the form below.

PROJECT COORDINATION
Other improvements to U.S. Route 54 in the vicinity include widening the eastbound traveled way, intersection improvements, washing the bridges over the Missouri River, and rehabilitation work on several bridges (north and south of the Missouri River).