Counties Impacted
Clay
Route Impacted
1
Work Type
Corridor Upgrades
In Progress

Project Milestones

Complete
Public Meeting

June 2024

milestone_icon
In Progress
Construction

Ongoing - Fall 2027

milestone_icon

Project Information

These projects are on Missouri Highway 1 (NE Antioch Road) from Missouri Route 152 south to NE 42nd Street.

The projects include the improvements below:

  • Pavement rebuild between NE 64th Street to NE 72nd Street
  • Pavement resurfacing between MO Route 152 to NE 72nd Street and between NE 42nd Street to NE 64th Street
  • Replacement of deficient curb and gutter from 64th Street to I-35
  • Slope stabilization on the west side between NE 43rd Street to NE 42nd Street
  • New pedestrian connection under I-35 from NE 44th Street to NE 43rd Street

Timeline

  • Work between MO Route 152 and NE 72nd Street is complete.
  • Work from the intersection of MO 1 and NE 72nd Street to 64th Street is complete. 
  • Work between just north of 64th Street and I-35 is ONGOING until Fall 2026. 
  • Work under I-35, between 43rd Street and 44th Street will be advertised fall of 2026 and is anticipated to be complete in the summer of 2027. 

How will this Project impact Motorists?

The posted speed limit will be reduced during construction.  

  • Pavement resurfacing operations will be conducted under lane closures. 
  • Slope stabilization and sidewalk work will be constructed on the shoulders with minor encroachments. 

Budget

  • Approx. $24 million

Image
questions

For More Information:

We're here to help. If you need additional information, you may contact our customer service line or contact Area Engineer Ravi Neupane:

Image
j

Public Meeting Information

A public meeting was held from 4-6 p.m. on Tuesday, June 11, 2024, located at Northland Neighborhoods INC, 5340 Chouteau Trafficway, Kansas City, MO 64119. 

 

Displays from Meeting
Image
Contact us infographic

Comment Period

There was an option to leave comments online beginning at 4 p.m. on Tuesday, June 11, 2024, until 4 p.m. on Tuesday, June 25, 2024. The online commenting period was available on the project webpage.

Embed
Is Responsive
Embed Code

PROJECT CONTACTS

Contact Photo
photo
Ravi Neupane
Title
Area Representative
Department
Kansas City District
Contact Info

Clay, Ray, and Platte Counties

(816)-607-2264

ravi.neupane@modot.mo.gov

Contact Photo
Jodie Puhr
Jodie Puhr
Title
Project Manager
Department
Kansas City District