St. Joseph, Mo. – The following is a list of general highway maintenance and construction work the Missouri Department of Transportation has planned in the Northwest Missouri region for the week of April 27-May 3.
There may be moving operations, such as mowing, brush cutting and litter removal, throughout the region in addition to the work mentioned below. Inclement weather may cause schedule changes in some of the planned work. Check the MoDOT Traveler Information Map at http://traveler.modot.org, or download the app for updated information.
MoDOT asks drivers to work with us by buckling up, putting your phone down, slowing down and moving over in work zones.
Andrew County
Route CC – Bridge maintenance at the bridge over I-29, April 27-30. The bridge will be narrowed to one lane with temporary traffic signals.
Atchison County
U.S. Route 136 – Resurfacing and drainage improvement project through July 2026. The road will be narrowed to one lane, and a 10-foot width restriction will be in place. (Contractor: Herzog Contracting Corp.)
Routes 46, 111, V, B, C – Various bridge rehabilitation projects through May 2026. The bridges may be narrowed to one lane with flaggers. (Contractor: Capital Paving & Construction LLC). *2
Buchanan County
Interstate 29 – Northbound lanes narrowed to one lane overnight with short-term rolling closures while crews set new bridge girders for the Gene Field Road Bridge, April 28. 7 p.m. to 10 a.m. Motorists should expect delays. (Contractor: Clarkson Construction Company). https://www.modot.org/projects/gene-field-road-bridge-replacement-over-interstate-29-buchanan-county.
- I-29 ramp to Route 6 (Fredrick Boulevard) will be closed between 9 p.m. and 5 a.m. due to rolling closure.
Gene Field Road Bridge – CLOSED for a bridge replacement project through July 2026. (Contractor: Clarkson Construction Company). https://www.modot.org/projects/gene-field-road-bridge-replacement-over-interstate-29-buchanan-county.
U.S. Route 59/Route 752/Route U – Intersection improvement project through spring 2027. (Contractor: Amino Bros. Co., Inc.) https://www.modot.org/projects/route-u-missouri-route-59-and-missouri-route-752-intersection-improvements-buchanan-county.
U.S. Route 169 – CLOSED for an intersection improvement project at Southeast Riverside Terrace through mid-July 2026. (Contractor: Hoy Excavating, LLC) https://www.modot.org/projects/us-route-169-intersection-improvements-buchanan-county.
U.S. Route 169 – Intersection improvement project at Route FF through mid-August 2026. A 10-foot width restriction will be in place. Access to 49th Street will be closed through June 2026. (Contractor: Leavenworth Excavating & Equipment Company, Inc.)
I-229 – CLOSED overnight at the southbound ramp to Route A for sign maintenance, April 29, 7 p.m. to midnight.
U.S. Route 36 & Route AC (Riverside Road) – narrowed for core drilling on U.S. Route 36, Route AC, and the bridge on/off ramps, April 30 – May 1. Flaggers may be present to guide traffic through the work zones on Route AC.
Caldwell County
Route 13 –Resurfacing and ADA improvements project from Samuel Street to School Street in Hamilton through mid-May. Route 13 will be narrowed to one lane with flaggers. (Contractor: Herzog Contracting Corp.).
Carroll County
Route 41 – CLOSED around-the-clock at the Wakenda Chute Bridge until further notice for bridge deck repairs.
Route 10 – Pavement repair and resurfacing project from Route FF to Route C in Ray County, through May 15. The road will be narrowed to one lane with flaggers guiding motorists through the work zone. (Contractor: Emery Sapp and Sons LLC).
Chariton County
Route EE -- ADA improvements project from Route 139 to just west of Walnut Street in Sumner, through April 2026. (Contractor: Ti-Zack Concrete, LLC).
Route CC – ADA improvements project from Fifth Street to Felt Street in Mendon, through April 2026. (Contractor: Ti-Zack Concrete, LLC).
Route F – CLOSED for a culvert replacement from Demsey Road to Hess Road, April 27, 7 a.m. to 3 p.m.
Route F – CLOSED for a culvert replacement from Hess Road to German Road, April 28-29, 7 a.m. to 3 p.m. daily.
Route F – CLOSED for a culvert replacement from Route M to Hess Road, April 30-May 1, 7 a.m. to 3 p.m. daily.
Clinton Couty
I-35 – Pavement rehabilitation in the southbound lanes from Exit 40 (Lathrop) to Exit 48 (south Cameron) through September 2026. Both north and southbound traffic will be one lane, each direction, in the northbound lanes (Contractor: Michels Road & Stone). https://www.modot.org/projects/interstate-35-and-us-route-69-concrete-overlay-clinton-county.
I-35 – Utility/permit work at the 51.4 mile marker, May 2-4. North and southbound lanes will each be narrowed to one lane around the clock. Motorists should expect delays. (Contractor: Black & McDonald).
- Short-term rolling closures north and southbound from U.S. Route 36 to U.S. Route 69 to pull utility lines across the interstate, May 2.
- Route BB ramps to southbound I-35 will have short-term intermittent closures, during the rolling closures, May 2.
Daviess County
Route 13 – Resurfacing and ADA improvements project from Berry Street to Van Buren Street in Gallatin through mid-May. Route 13 will be narrowed to one lane with flaggers. (Contractor: Herzog Contracting Corp.).
Route K – CLOSED for a culvert replacement from Route P to Hope Avenue, April 27-28, 6 a.m. to 4:30 p.m. daily.
Route PP – Seal coat overlay from Route Z to Drake Avenue, April 28.
Gentry County
Route EE – Seal coat overlay from Route T to Route P, April 29.
Grundy County
Route J – Scrub seal project, April 29-May 5. The road will be narrowed to one lane with a pilot car. (Contractor: Vance Brothers, Inc.).
Holt County
Routes B, 111, 59, C, N – Various bridge rehabilitation projects through May 2026. The bridges may be narrowed to one lane with flaggers. (Contractor: Capital Paving & Construction LLC). *2
Linn County
Route 11 – CLOSED at the Badger Creek Bridge, north of New Boston, for a bridge replacement project through the Northwest Bridge Bundle through May 2026. (Capital-Horner & Shifrin) *1
Route 139 – CLOSED at the Parson Creek Bridge, north of Meadville, for a bridge replacement project through the Northwest Bridge Bundle through May 2026. (Capital-Horner & Shifrin) *1
Route U – CLOSED at the Long Branch Bridge, northwest of Bucklin, through early May for a deck replacement project. (Contractor: Louis-Company, LLC). https://www.modot.org/projects/route-b-route-e-and-route-u-bridge-deck-replacement-grundy-and-linn-counties-0.
Route B – CLOSED at the Parsons Creek Bridge, west of Linneus, through June 2026. (Contractor: Louis-Company, LLC). https://www.modot.org/projects/route-b-route-e-and-route-u-bridge-deck-replacement-grundy-and-linn-counties-0
U.S. Route 36 – Concrete replacement from the Macon County line to Route 5, April 27-May 1. The westbound driving lane will be closed around-the-clock.
Livingston County
Route K – CLOSED at the North Fork Crooked Creek Bridge through April 2026 for a bridge replacement project through the Northwest Bridge Bundle. (Capital-Horner & Shifrin) *1
Mercer County
Route E – CLOSED at the West Medicine Creek Bridge through early June 2026 for a deck replacement project. (Contractor: E&C Bridge, LLC). https://www.modot.org/projects/route-e-route-ff-route-jj-and-route-oo-bridge-deck-replacement-multiple-counties.
Route E – CLOSED at the West Honey Creek Bridge through July 2026 for a bridge replacement project through the Northwest Bridge Bundle. (Capital-Horner & Shifrin) *1
Route D – CLOSED at the West Muddy Creek Bridge beginning Monday, April 27, through September 2026 for a bridge replacement project through the Northwest Bridge Bundle. (Capital-Horner & Shifrin) *1
Route E – Pothole patching from U.S. Route 65 to Route C, April 27-28.
U.S. Route 136 – Shoulder work eastbound at the bridge over Wildcat Creek, April 27-May 1.
Route J – Scrub seal project, April 29-May 5. The road will be narrowed to one lane with a pilot car. (Contractor: Vance Brothers, Inc.).
Route E – Scrub seal project, May 1-12. The road will be narrowed to one lane with a pilot car. (Contractor: Vance Brothers, Inc.).
Nodaway County
U.S. Route 71 – Resurfacing project from the Iowa state line to U.S. Route 136 near Burlington Junction through August 2026. The road will be narrowed to one lane, and a 10-foot width restriction will be in place.
Route 148 – Scrub seal project, April 27-May 1. The road will be narrowed to one lane with a pilot car guiding motorists through the work zone. (Contractor: Vance Brothers Inc.).
Route E – CLOSED for a culvert replacement from 170th Street to 160th Street, April 27, 7 a.m. to 3 p.m.
Route E – CLOSED for a culvert replacement from 160th Street to 150th Street, April 28-29, 7 a.m. to 3 p.m. daily.
Route E – CLOSED for a culvert replacement from 140th Street to 130th Street, April 30, 7 a.m. to 3 p.m.
Route 113 – Various bridge rehabilitation projects through May 2026. The bridges may be narrowed to one lane with flaggers. (Contractor: Capital Paving & Construction LLC). *2
Putnam County
Route N – CLOSED at the Turkey Creek Bridge through July 2026 for a bridge replacement project through the Northwest Bridge Bundle. (Capital-Horner & Shifrin) *1
Route FF – CLOSED at the Shoal Creek bridge through early June 2026 for a deck replacement project. (Contractor: E&C Bridge, LLC). https://www.modot.org/projects/route-e-route-ff-route-jj-and-route-oo-bridge-deck-replacement-multiple-counties.
Route E – Scrub seal project, April 27. The road will be narrowed to one lane with a pilot car guiding motorists through the work zone. (Contractor: Vance Brothers Inc.).
Route UU – Pothole patching from Route 5 to the Iowa state line, April 27-May 1.
Route 5 – Resurfacing project from U.S. Route 136 east of Unionville to Route 6 north of Milan, April 27 through July 2026. The road will be narrowed to one lane with a pilot car guiding motorists through the work zone. (Contractor: Emery Sapp & Sons, Inc.).
Sullivan County
Route 129 – CLOSED at the Spring Creek Bridge through August for a bridge replacement project through the Northwest Bridge Bundle. (Capital-Horner & Shifrin) *1
Route PP – CLOSED at the West Locust Creek Bridge through June 2026 for a bridge replacement project through the Northwest Bridge Bundle. (Capital-Horner & Shifrin) *1
Route T – CLOSED at the East Locust Creek bridge through July 2026 for a bridge replacement project through the Northwest Bridge Bundle. (Capital-Horner & Shifrin) *1
Route 5 – Resurfacing project from U.S. Route 136 east of Unionville to Route 6 north of Milan, April 27 through July 2026. The road will be narrowed to one lane with a pilot car guiding motorists through the work zone. (Contractor: Emery Sapp & Sons, Inc.).
Route P – Scrub seal project, April 27-28. The road will be narrowed to one lane with a pilot car guiding motorists through the work zone. (Contractor: Vance Brothers, Inc.).
Route E – Scrub seal project, April 28-30. The road will be narrowed to one lane with a pilot car guiding motorists through the work zone. (Contractor: Vance Brothers, Inc.).
Worth County
Route 46 – CLOSED at Marlowe Branch Creek for a bridge replacement project through May 2026. (Contractor: Emery Sapp & Sons) https://www.modot.org/projects/missouri-route-46-and-route-w-bridge-replacement-worth-county.
---
*1 This bridge is part of the NWBB (Northwest Bridge Bundle) program. The design-build team is Capital-Horner & Shifrin. More info: NWBB program web page.
*2 These bridges are part of the Safe and Sound Bridge Rehabilitation program. The contractor is Capital Paving & Construction, LLC. A full listing of bridges and project information can be found at: https://www.modot.org/projects/northwest-missouri-safe-sound-bridge-rehabilitations.
*3 In 2024, the Governor signed the Fiscal Year 2025 budget, including an additional $100 million to continue low-volume road improvements. This funding will be used to improve conditions on 1,985 lane miles of rural roads at 149 locations, including the ones listed below. For more information on the Governor’s Rural Roads Program, visit: https://www.modot.org/governors-rural-routes-program.
###