The Northwest Bridge Bundle will replace or rehabilitate up to 34 poor condition bridges in north central Missouri and bring them up to current standards. The majority of these bridges are on low-volume roads with less than 400 vehicles per day, though some carry a much higher traffic load. These bridges connect and serve the communities and citizens of rural northern Missouri. On average, these bridges have been in place for 71 years, with one bridge in Sullivan County reaching the 100-year mark in 2022.
Project Goals:
- Safely deliver the project within the program budget of $30 million on or before December 31, 2026.
- Use innovation and practical design to maximize the number of locations to be addressed.
- Provide quality, low maintenance structures and roadway approaches.
- Minimize the traveling public’s inconvenience through diligent construction efforts, flexibility in scheduling, and proactive communication.
Project Timeline
Four open house public meetings were held in March. A public comment period was available through April 11, 2023.
- Tuesday, March 7, 2023 – Keytesville High School, Keytesville
- Tuesday March 14, 2023 – Chillicothe High School, Chillicothe
- Tuesday, March 21, 2023 – Milan High School, Milan
- Tuesday, March 28, 2023 - Putnam County Library, Unionville
Click the links below to view all meeting materials:
Handout | Information Displays | County Map Displays
Spring 2023
Firms interested in receiving Northwest Bridge Bundle information sent a letter of interest to MoDOT by May 15, 2023.
The virtual industry meeting was held on May 23, 2023, at 10 a.m.
To request access to early release documents, email NWBridgeBundle@modot.mo.gov.
RFQ Forms & Documents:
DB-101 Major Participant Information
DB-102 Reference Project Summary
DB-107 Request for Clarification RFQ
DB-802 Debar Suspen Inelig Vol Exclusion Cert
MoDOT's Northwest Bridge Bundle team will evaluate the SOQs and create a short list of teams to further develop proposals for the project. The short list will be announced in June 2023.
The Request for Proposals will be released in July 2023 and will be due in the Fall of 2023.
After MoDOT's Northwest Bridge Bundle team scores the proposals, the Missouri Highways and Transportation Commission will award the Design-Build team contract at their December 2023 meeting to the team with the highest scoring proposal.
Once the Design-Build contractor is selected, a construction schedule will be developed and posted on this webpage, as well as in news releases and on social media.
Project News
-
Public invited to discuss bridge projects during final meeting
ST. JOSEPH, Mo. – The Missouri Department of Transportation (MoDOT) is planning a project to replace or rehabilitate up to 34 poor-condition bridges in north central Missouri, bringing them up to current standards. Known as the Northwest Bridge...
-
Public invited to discuss bridge projects
ST. JOSEPH, Mo. – The Missouri Department of Transportation (MoDOT) is planning a project to replace or rehabilitate up to 34 poor-condition bridges in north central Missouri, bringing them up to current standards. Known as the Northwest Bridge...
Project Manager

Michael Marriott
Title
Area Engineer
Department
Northwest District
Contact Info
Counties: Caldwell, Carroll, Chariton, Daviess, Grundy, Harrison, Linn, Livingston, Mercer, Putnam, Sullivan and the City of Cameron.
Email: michael.marriott@modot.mo.gov
Phone: 660-646-3218
Counties: Caldwell, Carroll, Chariton, Daviess, Grundy, Harrison, Linn, Livingston, Mercer, Putnam, Sullivan and the City of Cameron.