Counties Impacted
Montgomery
Project Status
Planning Phase
Route Impacted
19
70

Project Milestones

Complete
Public Meeting to Discuss Project Options
(Feb. 11, 2020)
Complete
Re-evaluation of I-70 Study - Environmental Impact Study
(November 2020)
Complete
Final Design Completed
Falls 2021 - Video Available About Project

Overview of Project   

If assistance is needed for another language or closed captioning, please contact necr@modot.mo.gov.

Complete
Right of Way Acquisitions
Fall 2021 - Spring 2022
Complete
Project Bid Opening to Contractors
June 2022
Complete
Project Awarded
(July 2022)
Contractor: Emery Sapp & Sons, Inc.
Contract Amt: $14.6M
In Progress
Construction
Anticipated to begin late Summer/Fall of 2022
Videos about construction