The safety and economic prosperity of Missourians depends, in part, on an I-70 that grows along with the state and nation. That’s why the Missouri Department of Transportation is working to improve I-70. Today, many portions of the facility are strained beyond capacity and outdated interchange designs which increase delays and dampen economic activity.
Missouri’s FY2024 budget from the General Assembly and signed into law by the governor provides $2.8 billion in General Revenue for the costs to plan, design, construct, reconstruct, rehabilitate and repair three lanes in each direction on nearly 200 miles of Interstate 70, from Blue Springs to Wentzville.
MoDOT has been working on the best plan to be efficient and innovative in how the 200 miles of I-70 will be delivered. As of May 2025, the Improve I-70 individual project limits have been updated and now include eight total project segments across the state. The nearly 200 miles will be broken into various contracts that will be awarded throughout 2029. Total completion of the corridor is anticipated by the end of 2030.
To date, five projects have been awarded and four projects are currently under construction. For more Improve I-70 project specific information, visit the Improve I-70 Projects page.
Projects Under Construction
- Columbia to Kingdom City
- Awarded: February 2024
- Construction: June 2024 - Late 2027
- Warrenton to Wentzville
- Awarded: November 2024
- Construction: March 2025 - Late 2028
- Blue Springs to Odessa
- Awarded: May 2025
- Construction: September 2025 - Late 2028
- Boonville to Rocheport
- Awarded: February 2026
- Construction: April 2026 - Late 2027
- Rocheport to Columbia
- Awarded: December 2025
- Construction: May 2026 - Late 2029
Upcoming Projects
- Truck Parking
- Scheduled Award: May 2026
- Construction: Fall 2026 - Late 2028
- Kingdom City to Warrenton
- Scheduled Award: November 2026
- Construction: Spring/Summer 2027 - Late 2030
- Odessa to Concordia
- Scheduled Award: Early 2027
- Construction: Spring/Summer 2027 - Late 2029
- Concordia to Boonville
- Scheduled Award: Spring/Summer 2027
- Construction: Fall 2027 - Late 2030
Download the PDF Version
Overall Timeline
MoDOT has designated an overall project team to guide the I-70 work across the state. This website will continue to serve as the information source for updates and public input as the plan for design and construction is developed.
Environmental Documents Updated: 2023-2024
- Environmental documents have been re-evaluated to identify any changes in the road and its conditions, traffic and environmental impacts since the studies were last completed in the mid 2000s. To view the 2023-2024 updated documents, click here.
Project Development: 2023-2024
- Project Development involves the design process and determines how the work should be broken into segments. MoDOT has worked with the private sector on plans to sequence project delivery based on traffic impacts and industry capacity to get the best value.
- The program has been divided into eight project segments. Additionally, a ninth project to improve and expand the availability of truck parking along the corridor is also been included in the program as part of a federal INFRA grant.
Project Award and Construction: 2024-2030
- To date, five Improve I-70 projects have been awarded and four are currently under construction across the state.
- All contracts will be awarded by 2029. Total completion of the corridor is anticipated by the end of 2030, dependent upon contractor and material availability.
The infographic above, also known as the Improve I-70 Placemat, summarizes what’s already under contract or completed, what’s funded in the state’s road and bridge program (the STIP) and in General Revenue.
Program Goals
The overall goal of the Improve I-70 project across Missouri is “to provide a safe, efficient, environmentally sound and cost-effective transportation facility that responds to corridor needs as well as expectations of a national interstate.”
Specifically, the focus is on the following:
- Provide a third lane of travel to eastbound and westbound I-70 from Blue Springs to Wentzville.
- Improve the interstate while modernizing the existing pavement and bridges.
- Increase the efficiency of freight movements along I-70.
- Minimize construction impacts with a focus on work zone safety, communication, and construction staging.
- Expand a diverse workforce through the creation of jobs.
In addition, the updated analysis of I-70 will include:
- Transportation Innovation – Upgrade the design to include technology for connectivity, intelligent transportation systems and other emerging transportation innovations.
Governor Parson and the General Assembly have provided a once in a lifetime investment into this critical transportation corridor. These 200 miles of I-70 are some of the first interstate to be built in the country 60 years ago. This is a monumental challenge to deliver, but MoDOT is the transportation expert. Along with our private sector partners in engineering and construction, we will deliver.
Latest Program News
-
New ramp opens connecting eastbound I-70 to southbound U.S. 63 in Columbia
JEFFERSON CITY, Mo. – A major milestone has been reached in reconfiguring the Interstate 70/U.S. Route 63 interchange in Columbia, with the opening of the first new ‘direct connect’ ramp this afternoon, Friday, Aug. 21, 2026
Opening much earlier...
-
MoDOT to close eastbound I-70 exit ramp to Wentzville Parkway overnight August 28-29
ST. CHARLES COUNTY – Crews with the Improve I-70 Warrenton to Wentzville Project will close the eastbound Interstate 70 exit ramp to Wentzville Parkway (exit 208) overnight Friday, August 28 and Saturday, August 29. Crews will be installing a...
-
Improve I-70: Blue Springs to Odessa Traffic Impacts
JACKSON & LAFAYETTE COUNTIES – The Missouri Department of Transportation is conducting the following traffic impacts along Interstate 70 for work on the Improve I-70: Blue Springs to Odessa project. All work is weather permitting.
Blue Springs Area...
-
I-70 WB to CLOSE in Odessa for Johnson Drive bridge demolition, Sept. 15-16
LAFAYETTE COUNTY – Crews will be conducting multiple traffic modifications in Odessa beginning on Tuesday, Sept. 15 for the demolition of the Johnson Drive bridge over Interstate 70.
Scheduled traffic modifications:
- I-70 westbound will close between...
-
MoDOT to close westbound I-70 lanes overnight at the I-70/I-64/U.S. 61 interchange August 24-28
ST. CHARLES COUNTY – Crews with the Improve I-70 Warrenton to Wentzville Project will close all westbound lanes of Interstate 70 at the I-70/I-64/U.S. 61 interchange overnight August 24-28. Crews will be doing work on the existing bridge girders. All...
-
Missouri Route 47 Bridge Over I-70 at Warrenton is Open to Traffic
HANNIBAL – The Missouri Route 47 at Warrenton opened to traffic late this evening, August 17, 2026 following a special “ribbon‑joining” ceremony to mark the completion of the bridge replacement project, over Interstate 70. The new bridge features a...
Stay Informed
Sign Up For Project/Construction Update Press Releases
To receive specific project updates and construction related press releases, sign up for Improve I-70 e-mails by visiting MoDOT e-Update and selecting one or more of the Improve I-70 options under the Improve I-70 heading. If you already have an e-Update account, you can login and adjust your e-mail preferences.