Counties Impacted
DeKalb
Project Status
Planning Phase
Route Impacted
Missouri Route A

Project Progress

In Progress
Design Phase

MoDOT has contracted with Olsson to design a bridge deck replacement project over Lost Creek on Route A in DeKalb County. The Design Phase also includes right of way acquisition (if any) and a public input period.

Not Started
Contractors bid on the project

The project is currently scheduled to be part of the October 2020 letting, when contractors may submit competitive bids for the project.

Not Started
Contract awarded

During its November 2020 meeting, the Missouri Highways and Transportation Commission may award the contract.

Not Started
Notice to Proceed

The Notice to Proceed date is the earliest date on which the contractor may begin work on the project. This project will have December 2020 Notice to Proceed, though the contractor may apply for an early Notice to Proceed, if they would like.

Not Started
Road Closure

In order to safely place the new bridge deck in the shortest amount of time, the bridge will be closed to all traffic during construction. An exact date for the closure has not yet been established. After the contract is awarded, the contractor will meet with MoDOT engineers and staff to determine the closure date.

Not Started
Completion and road reopening

The schedule for the reopening of the bridge has not yet been determined. After the contract is awarded, the contractor will meet with MoDOT engineers and staff to determine the duration of the closure.

Image
Bridge deck of Lost Creek Bridge on Route A north of Maysville

Old Bridge

Built in 1964, the current bridge is structurally deficient.

Image
J1S3136 DeKalb A Lost Creek Bridge redeck planned detour route

Planned Detour Route

A signed detour is currently planned over Routes 6, D and W . 

Frequently Asked Questions

 

Q. Why is MoDOT closing the road during construction?

A. Closing the road during the bridge replacement saves taxpayer money by allowing the contractor to work more efficiently and safely. This will result in a shorter construction period.

 

Q. How long will the road be closed?

A. The exact closure duration has not yet been established. Once the contract is awarded, the contractor will meet with MoDOT engineers and staff to determine the exact schedule, but according to estimates, it should not exceed 60 calendar days.

 

Q. What is the detour?

A. A signed detour is planned over Routes 6, D and W.

 

Q. Why not build a bypass?

A. Based on the cost/benefit ration, building a bypass would not be a prudent use of taxpayer funds. A bypass also could have negative impacts and disruption to private property.

 

Q. Who can I contact if I have further questions?

A. Questions about the project may be directed to MoDOT Customer Service at 888 ASK MODOT (1-888-275-6636Image removed.Image removed.). Or you may ask a question using the form below.

 

Q. How can I stay updated on the project's progress?

A. Sign up for project-specific updates using the form below.

Project News

  • North Missouri Rural Bridges Funded for Replacement

    10/19/2020

    HANNIBAL, Mo – Several rural bridges in northern Missouri will be replaced over the next few years thanks to a grant from the Federal Highway Administration.  “These bridges all have the same issues – they are weight restricted, supported by timber...

  • Atchison County Route B to close

    10/16/2020

    ROCK PORT, Mo – A crane crossing for the Outlaw windfarm project will close Route B for approximately three hours next week.

    Invenergy, the company installing the windfarm, plans to close Route B north of 155th Street on Tuesday, Oct. 20...

  • Planned Road Work for Northwest Missouri, Oct. 19 - 25

    10/16/2020

    St. Joseph, Mo. – The following is a list of general highway maintenance and construction work the Missouri Department of Transportation has planned in the Northwest Missouri region for the week of Oct. 19 – 25.

    All road closures and planned...

  • Nodaway County Route H to close

    10/15/2020

    MARYVILLE, Mo – A closure is once again planned on Route H in Nodaway County for a crane crossing as part of the White Cloud windfarm project.

    The closure of Route H at 375th Street is planned for a four-hour period between Sunday, Oct. 18, and...

  • Road closure scheduled for Route T in Amazonia

    10/14/2020

    AMAZONIA, Mo. – Railroad crews plan to close Route T in Amazonia this week to complete repairs at the St. Joseph Sub railroad crossing. The road will close between County Road 391 and Route K on Friday, Oct. 16, from 10 a.m. to 2 p.m. During the...

Webform
Have Project Questions or Feedback? Please use the form below to let us know.
*