Milestones

I-270 North project milestones

Complete
Community Advisory Group, Elected Officials meetings

Held January 30, 2018

milestone_icon
Complete
Initial public meeting

Held February 20, 2018 

milestone_icon
Complete
Disadvantaged Business Enterprise Symposium

Held March 4, 2018

milestone_icon
Complete
Pre-Industry meeting and Disadvantaged Business Enterprise mixer

Held February 26, 2019

milestone_icon
Complete
Second public meeting, and meeting with Community Advisory Group and elected officials

Held April 16,  2019

milestone_icon
Complete
Second Disadvantaged Business Enterprise Symposium

Held April 25,  2019

milestone_icon
Complete
Industry Meeting

Held April 30,  2019

milestone_icon
Complete
Request for Qualifications

Deadline was April 30, 2019

milestone_icon
Complete
Third Disadvantaged Business Enterprise mixer

Held June 20, 2019

milestone_icon
Complete
Request for Proposals

The deadline for any proposals from qualified contractor teams was June 26, 2019.

milestone_icon
Complete
Project Awarded

The Missouri Highway and Transportation Commission awarded the project to the contractor team providing the apparent best value on November 6, 2019.  The main members of that team were Millstone Weber and Parsons Transportation Group, supported by several other local consultants.

milestone_icon
Complete
Virtual public hearing

The virtual public hearing to share the concept with the apparent best value was on March 12, 2020.

milestone_icon
Complete
Virtual Groundbreaking

A virtual groundbreaking for the project was held on April 4, 2020. Construction started shortly thereafter.

milestone_icon
Complete
Ribbon cutting

The ribbon cutting for the project was held December 12, 2023.  Ribbon Cutting program