Counties Impacted
Jasper
Route Impacted
HH
Work Type
Roundabout Construction
Highway Feature
Dr. Russell Smith Way
In Progress

Project Milestones

Accepting Bids
November 30, 2023
milestone_icon
Project Awarded to Contractor
January 2024
milestone_icon
Construction Begins
May 2024
milestone_icon
Project Completion
February 22, 2025
milestone_icon

Purpose and Need/What's the Problem?

There are two closely spaced intersections that need to be combined into one to improve safety and accommodate increased traffic from future development in the area.

Project Information:

Contractor will combine the intersections of Jasper County Route HH (Fir Road) with Dr. Russell Smith Way (Southwest Outer Road) and the I-49 southbound ramps into a single lane roundabout.

News Releases

Frequently Asked Questions:

What is the need for this project?

There are two closely spaced intersections that need to be combined into one to improve safety and accommodate increased traffic from future development in the area.

Why a roundabout instead of keeping the traffic signals?

Signalized intersections have approximately 20-30 conflict points, or spots where vehicles could collide, roundabouts reduce that number to eight. Fewer conflict points, combined with slower speeds and calmer traffic, translate into as much as 76 percent fewer crashes.  Signals also increase the delay of the travelling public due to a signal's cycle time.  With a roundabout, an approaching vehicle does not have to come to a complete stop unless there is already a conflicting vehicle inside the roundabout’s circle.

Will there be a signed detour?

No, the intersection improvements will be made while allowing traffic to continue to flow. However, drivers can expect occasional lane closures, with traffic through the work zone controlled by flaggers. There will be inevitable delays and drivers are encouraged to find alternate routes to avoid the work zone.

Will I still be able to get to Mercy Hospital?

Yes, one of the first things the contractor will do is build a temporary access road to Mercy Hospital.

Will any property be impacted?

Right-of-way and construction easements were acquired from three parcels.

How do I ask a question about this project or leave feedback?

You may e-mail your questions/comments to swcr@modot.mo.gov or call (417) 895-7600.