Counties Impacted
Laclede
Route Impacted
B
Work Type
Bridge Deck Replacement
Highway Feature
Osage Fork
Planning Phase

The Laclede County Route B bridge over the Osage Fork of the Gasconade River was built in 1964. While the supporting structures are in good condition, the driving surface has deteriorated and needs replaced. The new bridge deck will be wider with new guardrails on all four corners.

PROJECT PROGRESS

Complete
Planning and Design Phase

The Missouri Department of Transportation and its consultant designed a new deck to extend the functional life of the bridge. The new deck will be wider at 26 feet (the existing structure is 24 feet). In addition, all four corners of the bridge will have new guardrail installed.

milestone_icon
Complete
Public Input
Comment period: Nov. 1 – 15, 2023.

Public Meeting

An online, virtual public meeting was held Nov. 1 - 15. Downloadable exhibits outlined the work being planned and the proposed detour to be used during construction.

The public was invited to leave comments and questions for the project team, either online or by mail. Mailed-in comments should be postmarked on or before Nov. 15 and addressed to:

Missouri Department of Transportation

Re: Laclede County Route B Bridge over Osage Fork Project
1511 Missouri Boulevard
Jefferson City, MO 65109

Comments were also accepted via an online form (active Nov. 1 - 15).

Meeting Exhibits

At the links below, find all available exhibits regarding the new bridge deck.

milestone_icon
Complete
Project Letting, Award, and Notice to Proceed

As part of their March 2024 meeting, the Missouri Highways and Transportation Commission awarded a $1,136,034.00 contract for this work to E & C Bridge, LLC. At that time the contractor was given an April 8, 2024, notice to proceed date - the earliest date they could begin work - and a Dec. 1, 2024, completion date.

milestone_icon
Not Started
Project Construction, Traffic Impacts, and Completion

At this time, construction is anticipated to be completed by Dec. 1, 2024. Route B over the Osage Fork will be closed for approximately 12 consecutive weeks with a signed detour in place.

milestone_icon

PROJECT MATERIALS

FREQUENTLY ASKED QUESTIONS

Why is MoDOT replacing the bridge deck?

The supporting elements of the bridge, built in 1964, are in good condition. However, the driving surface has deteriorated to a point where deck replacement is necessary. The new deck will be wider at 26 feet (the existing structure is 24 feet). In addition, all four corners of the bridge will have new guardrail installed.

The contractor will close the bridge to all traffic during construction, which is expected to take roughly 12 weeks. A signed detour will be posted over Missouri Routes 32 and 5 and Laclede County Route O.

The Long Ford River Access Area, immediately south of the bridge, will remain open through the project. Access directly underneath the bridge may be restricted during some portions of the project.

You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference Laclede County Route B over the Osage Fork Bridge Project on your inquiries. 