Project Overview:

The project included plans to repair and replace deficient sidewalks and upgrade pedestrian facilities at various locations along Missouri Route 163 from Vandiver Drive to Route K in Columbia.

Cost:

The total cost is approximately $900,000.

Why was this work necessary?

The ADA improvements are needed to bring sidewalks and intersections along Route 163 into compliance with the federal Americans with Disabilities Act of 1990. These improvements will provide safer access for all pedestrians and especially those with disabilities.