Counties Impacted
Clay
Completed

Project Update

Complete
Project Update: Sept. 19, 2022

Crews will work to remove and rebuild the shoulders of the roadway on Missouri Route 1, from approximately 7 a.m. until 4 p.m., Sept. 19-Oct. 21. This work will take place on southbound Route 1 from Route 210 to south of I-35. This work will require a flagging operation at times during the completion of the work. While one lane will remain open, motorists should expect delays in the area. After completion of the shoulder work on southbound Route 1, crews will begin on the shoulder of northbound Route 1. 

milestone_icon
Complete
Project update: 9/1/2022

Crews are completing work on the project that will not have an impact to traffic. This work includes:

  • ADA improvements including new sidewalks
  • Partial and full depth repairs

This work is taking place in conjunction with the following lane closures during weekdays, 7 a.m. to 4 p.m., Aug. 22-mid-September. 

Route 1 from south of I-35 to Parvin Road: The southbound lane of Route 1 will be closed from south of I-35 to Parvin Road. Once work is completed in the southbound lane, crews will move to the northbound lane of Route 1 from south of I-35 to Parvin Rd.

Route 1 from Parvin Road to Route 210: The southbound lane of Route 1 will be closed from Parvin Road to Route 210. Once work is completed in the southbound lane, crews will move to the northbound lane of Route 1 from Parvin Rd. to Route 210.

milestone_icon
Complete
Project update: 8/22/2022

Route 1 Resurfacing project begins. 

This work will require various lane closures on Route 1 from Missouri Route 210 to south of Interstate 35. One lane will remain open at all times. This project will require a flagging operation and motorists should expect delays in the area. All work is weather permitting.

The following lane closures are expected from beginning at 7 a.m. to 4 p.m., Aug. 22-mid-September 

Route 1 from south of I-35 to Parvin Road: The southbound lane of Route 1 will be closed from south of I-35 to Parvin Road. Once work is completed in the southbound lane, crews will move to the northbound lane of Route 1 from south of I-35 to Parvin Rd.

Route 1 from Parvin Road to Route 210: The southbound lane of Route 1 will be closed from Parvin Road to Route 210. Once work is completed in the southbound lane, crews will move to the northbound lane of Route 1 from Parvin Rd. to Route 210.

milestone_icon

Project Details

After careful study (pavement cores and observation of pavement surface) by MoDOT's pavement engineers, it has been recommended that the travel lanes of Route 1 from Route 210 to the ramps at south I-35 should undergo a 1 3/4' mill and fill roadway improvement plan. It's also been determined that the shoulders should be reconstructed (replaced).  The suggested changes would help improve motorist safety. 

What is MoDOT doing on this project? 

MoDOT plans to resurface the pavement, replace the shoulders, and complete ADA improvements along Route 1 from Route 210 to the south ramps at I-35. 

Why is this work being done?

It has been determined that the pavement along this stretch of roadway is deteriorating and safety is now a concern.

What is the timeline for this project? 

Work on this project is anticipated to begin June 2022. The project will now begin on Aug. 22, 2022. 

The completion date will remain the same. Completion of the project is expected for December 2022. 

Will this work impact traffic?

While one lane will remain open during the project, there may be times when motorists experience delays in the open lane during construction. 

How much will this project cost? 

The estimated cost of this project is $1.5 million  

Who is paying for this work/project? 

This project is being funded by MoDOT.

Project News

  • Lane closure on Missouri Route 1, Sept. 19-Oct. 21

    09/16/2022

    Crews will work to remove and rebuild the shoulders of the roadway on Missouri Route 1, from approximately 7 a.m. until 4 p.m., Sept. 19-Oct. 21. This work will take place on southbound Route 1 from Route 210 to south of I-35. This work will require...

  • Various Lane closures scheduled for Missouri Route 1

    09/09/2022

    Crews will continue repairs on Missouri Route 1. This work will require various lane closures on Route 1 from Missouri Route 210 to south of Interstate 35. While one lane will remain open, this project will require a flagging operation and motorists...

  • Various Lane closures on Missouri Route 1 to begin Aug. 22

    08/19/2022

     

    Crews will begin repairs on Missouri Route 1 (N. Prather Rd.). This work will require various lane closures on Route 1 from Missouri Route 210 (Armour Rd.) to south of Interstate 35. This is not a complete closure and one lane will remain open to...

Route 1 Resurfacing Project photos

Embed
Summary

The Route 1 Resurfacing project is designed to improve roadway safety on Route 1 from Route 210 to south of I-35.

Is Responsive
Embed Code
Route 1 Resurfacing

Online Public Information Meeting

Those interested are able to review the information on this webpage, ask questions, and leave comments about the project using a provided webform located at the bottom of this webpage.  

We want to hear from you. Please leave a comment below: 

Webform