Counties Impacted
Caldwell
Route Impacted
D
Work Type
Bridge Replacement
Planning Phase

Project Summary

 A project to replace the Shoal Creek bridge on Caldwell County Route D, install guardrail and include approach work was originally programmed into the Statewide Transportation Improvement Program (STIP) to go out for contractor letting in December 2025.

Following a routine inspection, MoDOT closed the bridge on June 25, 2024, due to advanced deterioration throughout the bridge. MoDOT pushed the project up from a December 2025 letting to a January 2025 letting. The contractor may begin construction as early as spring 2025 and all work must be complete on or before Dec. 1, 2025, to meet contract requirements.

 MoDOT and consultants from Bartlett & West are designing a project to complete this necessary work.

Project Milestones

In Progress
Planning and Design Phase

MoDOT and consultants from Bartlett & West are designing a project which will replace the bridge’s structure and driving surface, rebuild the approaches and install guardrail.

milestone_icon
Not Started
Project Bidding and Award

Contractors may submit competitive bids during MoDOT's scheduled lettings. This project is scheduled to be a part of the January 2025 letting. The Missouri Highways and Transportation Commission will consider all submitted bids at its scheduled monthly meeting in February 2025. If the lowest submitted bid meets all necessary criteria, the MHTC may award contracts at that time.

milestone_icon
Not Started
Construction

MoDOT will work with the contractor to determine a schedule after the project is awarded. Motorists will need to seek an alternate route around the closure.

milestone_icon
Not Started
Completion

By contract, all work must be completed on or before Dec. 1, 2025.

milestone_icon

Project News

Frequently Asked Questions

Will there be a detour?

There will be no detour during construction and motorists will need to seek an alternate route around the closure. 

Will MoDOT need to acquire any Right of Way?

MoDOT and consultants from Bartlett & West are working to determine if right of way acquisition is needed. If new right of way is required to complete the project, the project manager will contact the affected property owners.

How can I stay updated on the project’s progress?

Use the form below to sign up for project-specific updates delivered directly to your email inbox.

For more information about this or other MoDOT projects, please contact our 24-hour Customer Service line at 888 ASK MODOT (1-888-275-6636).

Webform
Sign up for email updates:
*
*
*

Project Map

Embed
Caldwell County Route D bridge over Shoal Creek
Is Responsive
Embed Code
Image
Wide angle view of the Shoal Creek bridge from creek bank

Need More Information?

We're here to help! If you're looking for additional information, you can contact us at: 

  • nwcr@modot.mo.gov
  • 1-888-ASK-MODOT (888 275-6636) - reference Northwest District Caldwell Route D bridge replacement
  • Sign up for eUpdates: Customer Service Signon (mo.gov)