Third Creek and Mistaken Creek Bridge Replacements
The Gasconade County Route A bridge over Third Creek, south of Mount Sterling, and the Osage County Route D bridge over Mistaken Creek, west of Cooper Hill, were replaced in 2020.
Both bridges are included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state.
Project Details
When:
The project took place during the 2020 construction season.
Cost:
$1,634,467
Work Taking Place:
Replacement of the Gasconade County Route A bridge over Third Creek, south of Mount Sterling, and the Osage County Route D bridge over Mistaken Creek, west of Cooper Hill.
Project Milestones
The Missouri Highways and Transportation Commission approved a contract with Don Schnieders Excavating, which submitted the low bid of $1,634,467.
PROJECT NEWS & UPDATES
-
Osage County Route D Bridge Replacement to Begin Next Week
OSAGE/GASCONADE COUNTY – Following the replacement of the Gasconade County Route A bridge over Third Creek, a contractor working for the Missouri Department of Transportation will begin the replacement of the Osage County Route D bridge over Mistaken...
-
Two County, Two Bridge Replacement Project to Begin Monday
GASCONADE/OSAGE COUNTY – Two 65-year-old bridges in need of replacement will require the closure of two roadways in Gasconade and Osage Counties in the coming months.
A contractor working for the Missouri Department of Transportation will begin...

Stay Connected!
Check out facebook.com/modotcentral and @MODOT_Central on Twitter to follow us and know what's happening near you! You can also click the button below to subscribe to district news and have the information sent straight to your inbox!