Counties Impacted
Audrain
Route Impacted
Business Route 54
J
15
22
Work Type
Sidewalk/ADA Improvements
Planning Phase

news Project Summary

The Missouri Department of Transportation (MoDOT), working with its consultant Bartlett & West, is preparing for a future project that will include resurfacing and sidewalk improvements at various locations on Business 54, Route J, Liberty Street, Missouri Route 15 and Missouri Route 22 in Mexico. Sidewalk improvements are being completed as part of MoDOT's initiative to bring all MoDOT facilities into compliance with the current standards of the American's with Disabilities Act (ADA).

Project Milestones

Complete
Public Meeting

May 1, 2025

milestone_icon
Complete
Right of Way Acquisition

June 2025 through October 2025

milestone_icon
Letting

April 2026

milestone_icon
Under Contract

May 2026

Contractor:  Magruder Paving, LLC
Contract Amt:  $4,272,501.19

milestone_icon
Not Started
Under Construction

Summer 2026

milestone_icon
Project Completion

Summer 2027

milestone_icon
Image
Public engagement

Project Information and Public Engagement

 

Public Meeting – May 1, 2025 | 4:00 - 6:00 p.m.

Location: Basement Meeting Room at Audrain County Courthouse, 101 N. Jefferson St., Mexico, MO

Sign up for E-update and text alerts.

news News Releases

Embed
Project Map
Is Responsive
Embed Code

project Project Contacts

Contact Photo
brian untiedt
Brian Untiedt
Title
Project Manager
Department
Northeast District
Contact Info

Email: Brian.Untiedt@modot.mo.gov

Phone: (573) 248-2442

Contact Photo
Emily Edgar
Emily Edgar
Title
Area Engineer
Department
Northeast District
Contact Info

Email: emily.edgar@modot.mo.gov

Phone:  573-248-8688

 

 

Frequently Asked Questions

How much does the project cost?  

Approximately $4 million

What are the anticipated impacts?  

Construction details have not been finalized at this time.  MoDOT will work with residents and business owners to ensure access is available during construction.

Will the road be closed during construction?  

Various traffic impacts will be in place as the project progresses. MoDOT will make every reasonable effort to reduce delays due to construction. Customers can anticipate temporary traffic impacts throughout the project. More information regarding traffic impacts will be shared through news releases and social media for each stage of construction as details become available.

Will MoDOT need to acquire any right of way?  

Yes. In 2025, MoDOT's Right of Way staff and consultants will begin the process of contacting property owners for any necessary right of way needed for the project. Right of way discussions are anticipated to continue through 2026. 

How can I stay updated about the project? 

Stay updated on news about roadwork in your area by signing up for emails at eUpdates at MoDOT.org

Who can I contact if I have further questions? 

Questions about the project may be directed to Brian Untiedt, MoDOT's project manager overseeing the project at brian.untiedt@modot.mo.gov or Emily Edgar, Area Engineer, at Emily.edgar@modot.mo.gov