The purpose of the project is to improve the flow of traffic and safety along the Route K corridor in Cape Girardeau County. Traffic studies completed in 2022 and 2024 looked at the corridor from County Road 319 to 0.20 miles east of County Road 317.
Multi-Stage Project Slated to Begin May 2026
Construction of the Route K corridor project in Cape Girardeau County is slated to begin this May. The project includes constructing a roundabout at Notre Dame High School, adding a center two-way left turn lane west of County Road 319 to Cape Girardeau, and adding an eastbound lane starting at Notre Dame Drive and tying into the existing eastbound 5-lane section near Wal-Mart's entrance.
Work will be staged and will be underway Monday, May 11, 2026 through Monday, Nov. 1, 2027, weather permitting. The stages will include:
- Stage 1: Work will occur on the north side of Route K and includes constructing the new Notre Dame Drive and extending two box culverts.
- During this stage, work will be completed in phases from CRD 319 to east of Notre Dame Drive, Notre Dame Drive to east of CRD 317, and then from west of CRD 317 to Siemers Drive.
- This stage will have minimal impacts on traffic.
- Tentatively, Stage 1 will be underway May 2026 through fall 2026.
- Stage 2: Work will occur on the south side of Route K and includes a majority of the roundabout construction.
- During this stage, work will be completed in phases from west of CRD 319 to east of Notre Dame Drive, west of Notre Dame Drive to East of Onyx Lane (roundabout construction), and West of Onyx Lane to Cape Girardeau.
- Tentatively, Stage 2 will begin in late fall 2026.
- This stage will have minimal impacts on traffic.
- Stage 3: The north side of the roundabout will be constructed in approximately 1.5 to 2 months.
- Stage 4: Work will remove the old Notre Dame Drive and add pavement east of Notre Dame on the south side of Route K. This will be underway for approximately 1.5 to 2 months.
This project will be completed in an effort to improve safety and traffic flow along the Route K corridor.
The route will remain open throughout construction, with minor lane shifts under flagger control. As needed, the driving lane will be reduced to a 10-foot width restriction. The work zone will be marked with signs. Motorists are urged to use extreme caution while traveling near the area.
Public Meeting Held April 18, 2024
The Missouri Department of Transportation held a public meeting from 4 to 6 p.m. Thursday, April 18 to discuss plans to improve the Route K corridor in Cape Girardeau, Missouri. The meeting was held at Notre Dame High School, located at 265 Notre Dame Dr. in Cape Girardeau, Missouri.
If you missed the public meeting, the meeting handout and exhibits are included below.
Traffic studies completed in 2022 and 2024 looked at the corridor from County Road 319 to 0.20 miles east of County Road 317. The proposed project includes widening the roadway, adding a center turn lane and constructing a roundabout at Notre Dame Drive. Construction could begin as early as spring 2026, with completion anticipated by fall 2026. It is anticipated the route would remain open throughout all phases of construction, with minor lane shifts under flagger control.

PROPOSED IMPROVEMENTS
Center Two-Way Left Turn Lane
Widening the roadway to accommodate a center two-way left turn through the study area
Benefit: This will allow vehicles to safely stop in center turn lane before making a left turn, which will reduce the likelihood of rear end crash occurrences within the corridor.
Widening
Widening for an additional eastbound lane starting at Notre Dame Drive and tying into existing eastbound 5-lane section near Wal-Mart's entrance in Cape Girardeau, Missouri
Benefit: This will help during peak times and as traffic capacity increases.
Intersection Improvements
Intersection improvements at Notre Dame Drive
Benefit: This will be completed in an effort to improve safety, address capacity needs and mitigate traffic delays during peak hours at Notre Dame Drive.
SUMMARY OF OTHER PROPOSED CORRIDOR IMPROVEMENTS
Sight Distance Design Phase Analysis Recommended
- CR 318
- CR 203
- CR 317
- Notre Dame Dr/Parkwood Lake St
Pavement Markings
- Install stop bars on minor street approaches
Signing
- Analysis during design to determine need for curve and intersection warning signs
- Add advance school warning signs on Route K approaches to Notre Dame Drive and replace existing School Speed Limit signs with new, high visibility fluorescent yellow signs
Right Turn Lanes
- Greenbriar Drive
- CR 318
- CR 206
- Notre Dame Dr
- CR 317 WB
Guardrail Design Phase Analysis Recommended
- Curve west of Notre Dame, on the northside of Route K
- Creek east of Notre Dame, both sides of Route K
- Curve at CR 203, both sides of Route K
Access Management Opportunities Design Phase
- Greenbriar Dr to S Forester Dr
- East of CR 317/Robin Lane to Walmart entrance (eastern project limits)
Meeting Materials
Project Timeline
Summer 2022
Fall 2022
Spring-Summer 2023
Jan.-Feb. 2024
Spring 2024
Fall 2024
May 11, 2026, weather pemitting
November 1. 2027, weather permitting
For More Information
Tim Pickett
Title
District Design Engineer
Department
Southeast District
Contact Info
(573) 472-9003
(573) 472-9003
Chris Crocker
Title
Project Manager
Department
Southeast District
Contact Info
(573) 380-1658
(573) 380-1658