Counties Impacted
Osage
Route Impacted
63
Work Type
Highway Realignment
Planning Phase

The current U.S. Route 63 corridor from south of U.S. Route 50 to the Maries River has a history of fatal and serious injury crashes. In the past 10 years, this corridor has seen 190 crashes that have resulted in seven fatalities, 12 serious injuries, and 80 minor injuries.

Image
Community members are a public meeting.

Public hearing

An open-house style public meeting will be held on Thursday, Aug. 21, 2025, at the Westphalia Knights of Columbus from 4:30 to 6 p.m. Members of the project team will be on hand to provide information, receive direct feedback, and answer questions from the community. There will be no formal presentation, so members of the public can come and go as they please. By participating and commenting, the public can help MoDOT determine what best serves the needs of the roughly 8,000 motorists who use the corridor on an average day while being responsible stewards of available funding.

PROJECT PROGRESS

Complete
Environmental Impact Statement

In 2006, U.S. Route 63 from U.S. Route 50 in Osage County to Rolla in Phelps County was ranked second out of 40 projects for future transportation needs by MoDOT and state planning partners. Subsequently, an Environmental Impact Statement (EIS) was conducted for this 47-mile section of U.S. Route 63. The EIS was completed in 2009 and identified the preferred alternative for improvements to this stretch of highway.

More information: https://www.modot.org/projects/us-route-63-environmental-impact-study-osage-maries-and-phelps-counties

milestone_icon
Complete
EIS Re-evaluation

The original EIS for this section of U.S. Route 63 underwent a re-evaluation that was completed and approved by the Federal Highway Administration in June 2025. A National Environmental Policy Act re-evaluation was necessary because existing conditions, possible solutions, potential impacts, and related mitigation measures may have changed.

More information: https://www.modot.org/projects/us-route-63-environmental-impact-study-osage-maries-and-phelps-counties

milestone_icon
In Progress
Planning, Design, and Right of Way Acquisition Phase

Based on the approved EIS, MoDOT is designing a new alignment for U.S. Route 63 in Osage County with the goal of improving safety and traffic flow. These improvements will require right-of-way acquisition.

milestone_icon
Not Started
Public Input
Aug. 6 – Sept. 4, 2025

During the four-week comment period running Aug. 6 – Sept. 4, 2025, the community and interested parties will have multiple avenues to learn about, ask questions, and submit input regarding the proposed realignment. 

  1. In-person - An open-house-style public hearing will be held Thursday, Aug. 21, 2025, from 4:30 to 6 p.m. at the Westphalia Knights of Columbus located at 819 Highway 63 in Westphalia. The project team will be on hand to answer questions, provide information, and receive input about the project. There will be no formal presentation, so attendees may come and go as they please at any time during the advertised hours.
  2. Online - All meeting exhibits will be available on this website, and feedback may be submitted using the form below.
  3. By email – Send comments to CDCR@modot.mo.gov with the subject line: U.S. Route 63 realignment in Osage County.
  4. By traditional mail – Comments may be mailed to Missouri Department of Transportation, 1511 Missouri Boulevard, Jefferson City, MO 65109, postmarked by Sept. 4, 2025. Please reference: U.S. Route 63 realignment in Osage County.
milestone_icon
Not Started
Project Letting, Award, and Notice to Proceed

The project is expected to be part of MoDOT's fall 2027 letting, when contractors submit competitive bids. If awarded by the Missouri Highways and Transportation Commission, a notice to proceed date will also be given. That is the earliest date the contractor may begin work.

milestone_icon
Not Started
Project Construction and Traffic Impacts

Construction could begin as early as fall 2027 and be completed in December 2029.

milestone_icon

COMING SOON

Corridor Map Crash Data Comment Forms (comment period runs Aug. 6 - Sept. 4, 2025) In-Person Informal Public Hearing Aug. 21, 4:30 - 6 p.m., open-house style so attendees can come and go at their convenience

FREQUENTLY ASKED QUESTIONS

This project will realign U.S. Route 63 from south of U.S. Route 50 to the Maries River in order to address safety concerns. In the past 10 years, this corridor has seen 190 crashes that have resulted in seven fatalities, 12 serious injuries, and 80 minor injuries. 

By expanding the current two-lane highway to a four-lane divided highway along a new alignment will also improve the flow of traffic.

In 2006, MoDOT and state planning partners presented 40 projects to address future transportation needs and ranked U.S. Route 63 from U.S. Route 50 in Osage County to Rolla in Phelps County as the second-highest need. Subsequently, an Environmental Impact Statement (EIS) was completed in 2009, with the re-evaluation completed in June 2025. 

Traffic impacts will not be determined until the new alignment is further along in the design process. 

You may email cdcr@modot.mo.gov or call us at 888 ASK MODOT (1-888-275-6636). Please reference U.S. Route 63 realignment in Osage County on your inquiries. 

Sign up for project-specific updates using the form below.

Project News

  • Input sought on realigning U.S. Route 63 in Osage County

    07/30/2025

     

    JEFFERSON CITY, Mo The current U.S. Route 63 corridor from south of U.S. Route 50 to the Maries River has a history of fatal and serious injury crashes. The Missouri Department of Transportation (MoDOT) is exploring a new realignment for U.S...

Webform
Sign Up for Project Updates via Email
*
*