Osage County Route N Bridge Replacement Over Contrary Creek

This project replaced the bridge over Contrary Creek on Osage County Route N, between US Route 50 and Route J, approximately 1.2 miles north of US Route 50.

This bridge is included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state.

 

Project Details

Cost:

The contract cost of the project is $633,921.

Work Taking Place: 

The former bridge over Contrary Creek was built in 1958 and reached a point where a bridge replacement was necessary.

Project Milestones

Complete
Bid Awarded

On October 7, 2020, the Missouri Highways and Transportation  Commission awarded the contract for the project to E & C Bridge, which submitted the low bid of $633,921. 

milestone_icon
Complete
Construction Begins

Work began on August 18, 2021. 

milestone_icon
Complete
Project Completion
Fall 2021

The work was completed, and the bridge reopened to traffic, on October 1, 2021. 

milestone_icon

Project News & Updates

  • Contrary Creek Bridge Replacement Begins Next Week

    08/06/2021

    OSAGE COUNTY – Contractors working for the Missouri Department of Transportation (MoDOT) will begin the process of replacing the Osage County Route N bridge over Contrary Creek on Wednesday, August 11.



    The bridge is located between U.S. Route 50 and...