Columbia Utility Work Project
A contractor working for MoDOT will be upgrading MoDOT fiber lines that connect traffic signals on state routes across the city. The upgrade will allow these signals to better communicate with each other. This will allow for improved signal timing and traffic flow. It will also help MoDOT respond in a timelier manner to signal issues, allowing crews to trouble shoot, monitor and make timing adjustments remotely in real time.
The contract was awarded to Meyer Electric, which submitted the low bid of $881,012.
Project Details
When: Crews will begin the week of June 22 on Route 740/Stadium Boulevard. The project is expected to be completed by the end of December.
Cost: $881,012
Work Taking Place: A contractor working for MoDOT will be upgrading MoDOT fiber lines that connect traffic signals on state routes across the city. The upgrade will allow these signals to better communicate with each other. This will allow for improved signal timing and traffic flow. It will also help MoDOT respond in a timelier manner to signal issues, allowing crews to trouble shoot, monitor and make timing adjustments remotely in real time.
Traffic Impact: There could be the occasional lane closure to traffic. Signs will guide motorists through the work zones. When crews work on Route 163/Providence Road, sidewalks will be closed to pedestrians. Pedestrians will be encouraged to use alternate walking paths.
Project Milestones
The contract was awarded to Meyer Electric, which submitted the low bid of $881,012
The work is expected to take place from June 22 - mid August
The work is expected to take place from mid August - end of August
The work is expected to take place from early September - late September. Sidewalks will be closed to pedestrians during this time.
The work is expected to take place from early October - late October
The work is expected to take place from late October - late November
The project is expected to be completed by late December
Project News & Updates
-
MoDOT Utility Work to Impact Columbia Traffic Next Week
COLUMBIA – Motorists in Columbia will see lane closures on two heavily traveled roadways in the coming week as part of a project to improve Missouri Department of Transportation traffic signal connectivity.
A contractor working for MoDOT is...
-
MoDOT Utility Work to Begin in Columbia Next Week
COLUMBIA – Motorists in Columbia may see short-term lane closures on state routes in the coming months as part of a project to improve Missouri Department of Transportation traffic signal connectivity.
A contractor working for MoDOT will be...