Projects Schedule Report -3c - July.2020

MoDOT’s customers expect transportation improvements to be completed and roadways opened quickly with minimal impact to their lives. Delivering projects by the contract completion date is the target for all projects and is considered a commitment to Missourians and drivers.

Embed
Is Responsive
Embed Code
Is Responsive
Embed Code
Is Responsive
Embed Code
Is Responsive
Embed Code
Is Responsive
Embed Code
Is Responsive
Embed Code

Results Driver

Contact Photo
travis koestner
Travis Koestner
Title
State Design Engineer
Department
Design
Contact Info

Email: Travis.Koestner@modot.mo.gov

Phone: (573) 526-0245

Measurement Driver

Contact Photo
dan oesch
Dan Oesch
Title
Project Director
Department
Central District
Contact Info

Email: Daniel.Oesch@modot.mo.gov

Phone: (573) 291-2788

Write Up:

MoDOT’s customers expect transportation improvements to be completed and roadways opened quickly with minimal impact to their lives. Delivering projects by the contract completion date is the target for all projects and is considered a commitment to Missourians and drivers. Completing projects on time helps maintain credibility with Missourians, minimizes drivers’ exposure to work zones and provides facilities in good condition that improve safety and reduce vehicle maintenance costs.

MoDOT works to meet the initial contract completion date by preparing accurate plans and quantities, setting aggressive but reasonable completion dates and setting liquidated damages to reinforce completion dates without undue bid risks. In fiscal year 2020, 74% of all closed out projects were completed by their planned completion dates.

Weather, additional work or a MoDOT directive sometimes necessitates an authorized extension of the completion date without any financial assessment to the contractor. In FY 2020, 83% of the closed-out projects were completed by the adjusted dates.

There are times when a contractor misses the contract completion date and the contractor is assessed damages. Of the road and bridge contracts completed in FY 2020 that did not meet the original contract date, five were extended due to weather delays, 26 were extended due to extra work, one experienced utility delays, 18 were extended by MoDOT and 49 missed the completion date with damages assessed totaling $1,239,800.00.

The target for this measure is to have at least 80% of projects completed by the original completion date.  At the end of FY 2020, the average number of all contracts completed by the original completion date was 74%.

Purpose of the Measure:

This measure tracks the percentage of road and bridge projects opened by the commitment date established in the contract. This commitment also includes local public agency projects and multimodal projects (rail, aviation, waterway and transit).

Measurement and Data Collection:

For road and bridge projects, the project manager collaborates with the project team to establish the project completion day which is specific to when the road or bridge project will be opened to the public so to eliminate a financial penalty. The resident engineer uses the SiteManager system to track and document the work. Local public agencies and multimodal agencies use staff or consultant resources to set contract completion dates and track performance.

The target for this measure was set by management directive.