Counties Impacted
Moniteau
Completed

Project Milestones

Complete
Bid Awarded
November 2019

The Missouri Highways and Transportation Commission approved a contract  with Gene Haile Excavating, which submitted the lowest bid of $849,329. 

milestone_icon
Complete
Burris Fork Creek Bridge Rehabilitation Begins
May 2020
milestone_icon
Complete
Medlen Creek Bridge Replacement Begins
July 2020
milestone_icon
Complete
Project Completion
Fall 2020
milestone_icon

This page provides information on the replacement of the bridge over Medlen Creek and the redeck project on the bridge over Burris Fork Creek on Missouri Route CC, north of Route C near High Point.

This bridge is included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state.

 

Why was this work necessary? 

The former Medlen Creek Bridge was built in 1967 and the condition of the bridge reached a point where a bridge replacement was necessary.

The existing Burris Fork Creek Bridge was built in 1967 and was in need of a deck replacement.

 
What will the project cost? 

The total contract was $849,329.