Project Milestones
The Missouri Highways and Transportation Commission approved a contract with Gene Haile Excavating, which submitted the lowest bid of $849,329.
This page provides information on the replacement of the bridge over Medlen Creek and the redeck project on the bridge over Burris Fork Creek on Missouri Route CC, north of Route C near High Point.
This bridge is included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state.
Why was this work necessary?
The former Medlen Creek Bridge was built in 1967 and the condition of the bridge reached a point where a bridge replacement was necessary.
The existing Burris Fork Creek Bridge was built in 1967 and was in need of a deck replacement.
What will the project cost?
The total contract was $849,329.