Counties Impacted
Franklin
Route Impacted
MM
Work Type
Safety and Operational Improvements
Planning Phase

Project Summary

This project will provide pavement resurfacing, guardrail and sign upgrades, add shoulders, curve realignment (at Union Pacific Railroad), and improve box culverts on Route MM from Route T to Route 100 in Franklin County.

Project Milestones

Complete
Project Design
July 2023
milestone_icon
Complete
Project Advertised
April 2024
milestone_icon
Complete
Contract Awarded
November 2024
milestone_icon
In Progress
Construction Begins
Winter/Spring 2024
milestone_icon

COST OF PROJECT

$6.7 Million

 

IMPACTS TO TRAFFIC

Driving lanes will be open throughout the duration of the project, except for a period in spring/summer 2024 when a section of the roadway will be closed to thru traffic at the Union Pacific RR overpass for five to seven weeks. During this time, through traffic will be diverted to Route 100 as the designated detour.  Other short-term lane closures are anticipated at various locations and times.

WHO TO CONTACT

Contact Photo
Stephen O'Connor Profile Picture
Stephen O'Connor, P.E.
Title
Area Engineer
Department
St. Louis District
Contact Info

Area Engineer, Franklin & Jefferson County Area 

(314) 453-5021

Stephen.OConnor@modot.mo.gov