MoDOT will replace the Chariton River Bridge on Missouri Route 6 near Novinger in Adair County. MO Route 6 will need to be closed two separate times during construction. The abandoned Norfolk Southern railroad bridge on Route 136, 1.2 miles west of Route 63 in Schuyler County also will be removed as a part of this contract.. U.S. Route 136 will be closed 40 days to remove the old bridge and construct new embankment and pavement in the same location.

Complete
Public Meeting October 6, 2022

Missouri Route 6: Adair County Handout

https://www.modot.org/media/40251

Route 6 Typical Section

https://www.modot.org/media/40248

Chariton Strip Map

https://www.modot.org/media/40249

Chariton Staging Display

https://www.modot.org/media/40250

milestone_icon
Complete
Construction

Construction began March 20, 2023 with completion estimated Fall 2023. (Adair Co, Missouri Route 6)

Construction began May 22, 2023  with completion estimated mid-July 2023 (Schuyler Co, U.S. Route 136)