Districts Impacted
Project Facts:
-
Replace Missouri Route 413 (Sunshine Street) bridge over MNA Railroad in Springfield
-
Add/improve pedestrian facilities on both sides of roadway from Scenic Avenue to Marion Avenue
Construction: Spring 2024
Estimated total project cost: $5,888,000
Completion Date: Winter 2024
Bridge Facts:
-
Bridge built in 1963
-
Bridge carries 26,164 vehicles a day
-
Old bridge 65 feet wide, 158 feet long
Traffic Impacts:
-
MO 413 (Sunshine St) CLOSED from east of Scenic Avenue to west of Marion Avenue for up to 4 months during construction
-
Detour: James River Freeway, Kansas Expressway, Chestnut Expressway, and US 160
Project Updates
-
MoDOT: Plans to Replace the Sunshine Street (Missouri Route 413) Bridge over MNA Railroad
Springfield – The public is invited to a virtual (online) public meeting starting Monday, January 30, to learn more about plans for the Sunshine Street (Missouri Route 413) Bridge Replacement and Pedestrian Improvements Project in Springfield, the...