Counties Impacted
Polk
Completed

Project Facts:

  • Replace Route 123 bridge over Barren Creek
  • Widen bridge to 26 feet

Construction: 2021

Estimated total project cost: $1,047,000

Bridge Facts:

  • Bridge built in 1948
  • Bridge carries 514 vehicles a day
  • Old bridge 22 feet wide, 102.5 feet long
  • This bridge is included in Gov. Mike Parson’s $351 million Focus on Bridges program, which will repair or replace 250 bridges across the state

Traffic Impacts:

  • Route 123 CLOSED at Barren Creek for up to 3 months during construction

  • Signed detour: Route 123, Route 32, Route 245, Route 215 and Route 123

Project Updates