Counties Impacted
St. Louis City
Route Impacted
100
Work Type
Pavement Resurfacing
Planning Phase

Project timeline

In Progress
Road Safety Audit site visit

MoDOT and its partners walk along the corridor to assess and document any current traffic trends and roadway conditions.

milestone_icon
Complete
Community and Focus Group Meeting #1

MoDOT and its partners will meet with an invited group of individuals  (a focus group) to discuss the corridor and potential issues that they observe. In addition, the department will listen to concerns from the public in a community meeting.

milestone_icon
In Progress
Conceptual development

With the information gathered from the site visit and the focus group, the design team will start developing some initial plans.

milestone_icon
Complete
Focus Group meeting #2

The department meets with interested stakeholders to get feedback on it's evaluations of the corridor and some insight on possible solutions proposed for the corridor.  

milestone_icon
Complete
Community Meeting #2

The department will share potential safety solutions. 

milestone_icon
Complete
Focus Group Meeting #3

Once some of the initial designs have been determined, the department will once again talk with a select group of stakeholders to verify that these concepts are in line with the vision that the community has shared.

milestone_icon
In Progress
Final Road Safety Audit completed

 

From the information gathered during the focus groups and the two community meetings, the initial conceptual plans will be modified and finalized.

milestone_icon
In Progress
Community meeting #3

A third community meeting will share the final plans for the corridor.

milestone_icon
Not Started
Construction begins

Construction on this project is slated to begin in late 2025, at this time.

milestone_icon

What’s currently underway:

The Missouri Department of Transportation has a resurfacing project set for Route 100 in the city of St. Louis. Route 100 follows Chouteau between Interstate 55 and Vandeventer, and follows Manchester from Vandeventer to the city limits. Since the department is resurfacing the roadway, it’s a great time to make investments, based on community input, on ways to make the roadway safer. The department has $2 million in safety funds that have been allocated to this project, beyond that needed for the resurfacing work. Between 2017 and 2021, this corridor had more than 1,500 crashes, which is roughly five times the state average for similar roadways. During that time, there were four fatalities, including one pedestrian; there were also 32 serious injury crashes, including six which involved pedestrians and three that involved cyclists. Previously, the department has held two public meetings – the first to identify possible safety concerns that people who live, work and travel along the corridor have, and the second to share potential safety countermeasures that could be included on the corridor. In addition, the department worked with a select group of individuals several times in smaller focus groups.

What improvements are being done?

Much of the corridor will have fewer lanes, except for the area through The Grove, due to the high volumes of traffic into and out of The Grove area. There is currently much more available space in the corridor than traffic, which tends to lead to increased speed and more aggressive driving.  Most areas will be reduced by one lane, with left turn lanes onto side streets.  To prevent traffic using the center lane as a passing lane, the department will create raised medians in those areas where the lanes are not needed. Remaining roadway space will be used for a buffered bike lane along much of the corridor. Pedestrian crossings will be enhanced, including more Rapid Rectangular Flashing Beacons along the corridor and updating striping. 

What about a protected bike lane?

We’ve heard from the community about their desire for a protected bike lane along the corridor.  Although MoDOT can’t install a vertical barrier along the corridor under the current agreement with the city, we are talking with the city to include those options along the corridor between Sarah and Broadway. Although that work won’t happen as a part of this project, we are moving toward an agreement for that in the future, as part of a separate project. 

How will MoDOT make mid-block crossings safer?

One of the concerns we heard from the public was that drivers tended not to stop as pedestrians were crossing the roadway, especially at mid-block crossings, even when the flashing signals were activated. This project will reduce the number of lanes across much of the corridor, and will narrow most of those lanes. This should reduce the amount of time it takes people to cross the street. In addition, many of the mid-block crossings will have a median refuge to allow pedestrians to stop, in a protected area, if they are unable to fully cross. This should help make the crossing safer for pedestrians. 

What about plantings in the median?

MoDOT continues to talk with our partner, the city of St. Louis, about options for aesthetic improvements to the corridor. As a matter of policy, MoDOT requires all aesthetics, such as plantings, to be paid for and maintained by a municipality or other government organization.

What are MoDOT’s responsibilities on Route 100?

MoDOT has a maintenance agreement with the city of St. Louis for certain roads within the city limits. MoDOT is responsible for maintaining signals, signs, striping, sweeping and pavement maintenance on Route 100. St. Louis City retains ownership and responsibility for everything else. During this process, MoDOT will work with the city of St. Louis to evaluate and consider other safety improvements outside of the above maintenance responsibilities.

For concerns beyond MoDOT’s responsibility, please contact the city of St. Louis citizens service bureau at 314-622-4800.

Project Timeline

September 2023  Project start
September 2023  Initial Road Safety Audit site visit
Fall 2023/winter 2024  First community meeting and first focus group
Winter - summer 2024  Development of improvement alternatives
Winter 2024 Second focus group
Spring 2024 Safety demonstration to test proposed improvements
Spring 2024  Third focus group to evaluate draft recommendations
Summer/fall 2024  Final community meeting to discuss final recommendations
2025  Road resurfacing project starts

 

Project contacts

Contact Photo
Jennifer Wade
Jennifer Wade, P.E.
Title
Area Engineer, city of St. Louis
Department
St. Louis District
Contact Info

Phone: (314) 624-7462

E-mail: Jennifer.Wade@modot.mo.gov

St. Louis Customer Service
Contact Info

slcrrep@modot.mo.gov

Phone 314-275-1500 or 1-888-ASK-MODOT (275-6636)