A project on Maries County Road 213 to replace the Fly Creek Bridge will be bundled with the Missouri Route 42 Maries River and Fly Creek bridge rehabilitation project and the Maries County Route AA Maries River and Little Maries River bridge rehabilitation project.
Only one of the five bridges in the bundle of projects, by contract, may be closed at a time.
As of Jan. 24, 2025, the project is scheduled to go out for contractor bids in May 2025 and construction will extend into 2026. The exact timeline for each bridge closure will be determined after the contract is awarded.