Counties Impacted
Taney
Stone
Project Status
Planning Phase

Project Facts

  • Replace the bridge on Route 86 over Long Creek arm of Table Rock Lake
  • New bridge located south of existing structure
  • Build new sections of pavement to connect bridge to Route 86
  • Install new guardrail at bridge ends

Construction: as early as 2022

Estimated total project cost: $36 million

Bridge History/Facts:

  • Built in 1956
  • Carries 8,611 vehicles a day
  • Urgent repairs made to bridge truss support system in June 2019 until long-term project can be built in 2022
  • Existing bridge experiencing deterioration of truss support system 

Project Updates/News Releases

  • TRAFFIC ALERT:

    07/15/2019

    Taney/Stone Counties – The Long Creek bridge which carries Missouri Route 86 across Table Rock Lake will be reduced to one-lane during the week of July 22 during an annual, routine safety inspection, the Missouri Department of Transportation said. 

    ...
  • MoDOT Decides Future Improvement Project

    06/21/2019

    Taney/Stone Counties – After hearing from the community and looking at the pros and cons for each option, the Missouri Department of Transportation has decided to replace the Long Creek bridge which carries Route 86 traffic across Table Rock Lake...

  • TRAFFIC ALERT:

    06/07/2019

    TRAFFIC ALERT! 

    Long Creek Bridge on Missouri Route 86 OPEN

    To Traffic Following Urgent Repairs to Support System

     

    Taney/Stone Counties – The Long Creek bridge which carries Missouri Route 86 across Table Rock Lake OPENED to traffic at 8...