Counties Impacted
Holt
Route Impacted
B
Completed

Project Progress

Complete
Design phase

MoDOT has contracted with Olsson to design a bridge deck replacement project over Interstate 29 on Route B in Holt County. The Design Phase also includes right of way acquisition (if any) and a public input period.

milestone_icon
Complete
Contractors bid on the project

The project was part of the October 2020 letting, when contractors submitted competitive bids for the project.

milestone_icon
Complete
Contract awarded

During its November 2020 meeting, the Missouri Highways and Transportation Commission awarded the $1,910,949.89 contract to Emery Sapp & Sons, Inc. The awarded amount also includes the bridge rehabilitation of the DeKalb County Route A bridge over Lost Creek.

milestone_icon
Complete
Notice to Proceed

The Notice to Proceed date is the earliest date on which the contractor may begin work on the project. This project had a December 2020 Notice to Proceed.

milestone_icon
Complete
Road Closure

In order to safely place the new bridge deck in the shortest amount of time, the bridge will be closed to all traffic during construction. The contractor plans to close the bridge to all traffic on Monday, April 19, 2021. That date is subject to change.

 

Prior to the bridge closure, shoulder work will be conducted on I-29 under the bridge.

 

For the duration of the project, I-29 may be narrowed to one lane with a 12-foot width restriction under the bridge.

milestone_icon
Complete
Completion and road reopening

The contractor was able to reopen the bridge to all traffic on July 16, 2021.

milestone_icon
Image
Holt County Route B bridge over I-29, bridge deck looking south taken November 2017

Old Bridge Deck

The deck of the bridge over I-29 on Route B in Holt County. This is a view of the bridge deck looking south, taken in November 2017.

Image
Detour Map for J1S3061

Planned Detour Route

The current planned signed detour route for the bridge deck replacement is over U.S. Route 59 and Route 120.

Frequently Asked Questions

Why is MoDOT closing the road during construction?

Closing the road during the bridge replacement saves taxpayer money by allowing the contractor to work more efficiently and safely. This will result in a shorter construction period.

How long will the road be closed?

The contractor plans to close the bridge to all traffic on Thursday, April 15 and should have the bridge reopened by Aug. 1, 2021.

What is the detour?

A signed detour is planned over U.S. Route 59 and Route 120.

Why not build a bypass?

Based on the cost/benefit ratio, building a bypass would not be a prudent use of taxpayer funds. A bypass also could have negative impacts and disruption to private property.

Who can I contact if I have further questions?

Questions about the project may be directed to MoDOT Customer Service at 888 ASK MODOT (1-888-275-6636)

How can I stay updated on the project's progress?

Sign up for project-specific updates using the form below.

For more information about this or other MoDOT projects, please contact our 24-hour Customer Service line at 888 ASK MODOT (1-888-275-6636) or sign up for alerts straight to your inbox at email/text updates.