Counties Impacted
DeKalb
Route Impacted
A
Completed

Project Progress

Complete
Design Phase

MoDOT has contracted with Olsson to design a bridge deck replacement project over Lost Creek on Route A in DeKalb County. The Design Phase also includes right of way acquisition (if any) and a public input period.

milestone_icon
Complete
Contractors bid on the project

The project was part of the October 2020 letting, when contractors submitted competitive bids for the project.

milestone_icon
Complete
Contract awarded

During its November 2020 meeting, the Missouri Highways and Transportation Commission awarded the $1,910,949.89 contract to Emery Sapp & Sons, Inc.

milestone_icon
Complete
Notice to Proceed

The Notice to Proceed date is the earliest date on which the contractor may begin work on the project. The contractor was given a Dec. 7, 2020 notice to proceed.

milestone_icon
Complete
Road Closure

In order to safely place the new bridge deck in the shortest amount of time, the bridge will be closed to all traffic during construction. The contractor intends on closing the bridge to all traffic on Monday, March 22.

milestone_icon
Complete
Completion and road reopening

The contractor intends to reopen the bridge to all traffic by the end of June 2021.

milestone_icon
Image
Bridge deck of Lost Creek Bridge on Route A north of Maysville

Old Bridge

Built in 1964, the current bridge is structurally deficient.

Image
J1S3136 DeKalb A Lost Creek Bridge redeck planned detour route

Planned Detour Route

Motorists will be directed over a signed detour on Routes 6, D and W . 

Frequently Asked Questions

 

Q. Why is MoDOT closing the road during construction?

A. Closing the road during the bridge replacement saves taxpayer money by allowing the contractor to work more efficiently and safely. This will result in a shorter construction period.

 

Q. How long will the road be closed?

A. The contractor plans to close the road to all traffic on Monday, March 22 and reopen it by the end of June 2021.

 

Q. What is the detour?

A. A signed detour is planned over Routes 6, D and W.

 

Q. Why not build a bypass?

A. Based on the cost/benefit ration, building a bypass would not be a prudent use of taxpayer funds. A bypass also could have negative impacts and disruption to private property.

 

Q. Who can I contact if I have further questions?

A. Questions about the project may be directed to MoDOT Customer Service at 888 ASK MODOT (1-888-275-6636Image removed.Image removed.)

 

Q. How can I stay updated on the project's progress?

A. Sign up for project-specific updates using the form below.

Project News

  • Lost Creek Bridge on DeKalb County Route A now open

    06/03/2021

    St. Joseph, Mo. – The Lost Creek Bridge, north of Maysville, on DeKalb County Route A is now open after a bridge deck replacement project. The Missouri Department of Transportation contracted with Emery Sapp & Sons, Inc. to complete the project. The...

  • DeKalb County bridge deck replacement project to begin soon

    03/11/2021

    St. Joseph, Mo. – The Lost Creek Bridge on DeKalb County Route A will close soon for a bridge deck replacement project. The Missouri Department of Transportation contracted with Emery Sapp & Sons, Inc. to replace the bridge’s deck. This bridge...

For more information about this or other MoDOT projects, please contact our 24-hour Customer Service line at 888 ASK MODOT (1-888-275-6636).