Counties Impacted
Carroll
Route Impacted
M
Work Type
Bridge Rehabilitation
Planning Phase
Updated 9/23/2022

The Grand River Bridge on Carroll County Route M was built in 1983, and carries approximately 300 vehicles per day. The driving surface of the 1,620-foot long bridge needs a preventive maintenance treatment and the supporting structures are showing signs of age and require repair. MoDOT is designing a project to complete this necessary work.

 

Route M will close at the bridge during the project which will go out for contractor bids as part of MoDOT's May 2023 letting and could be awarded to a contractor at the June meeting of the Missouri Highways and Transportation Commission.

Project Progress

In Progress
Planning and Design Phase

MoDOT's Planning and Design team are designing a project which will rehabilitate the bridge's driving surface and repair the super and substructures at the bridge.

milestone_icon
Complete
Open Comment Period

MoDOT solicited the public's input during an open comment period, held Sept. 6 - 20, during the project's Design phase. The comment period is now closed.

 

milestone_icon
Complete
Contract Letting, Award & Notice to Proceed

This project was part of MoDOT's May 2023 letting, when contractors submitted competitive bids on the project.

At their June 2023 meeting, the Missouri Highways and Transportation Commission awarded a $866,867.50 contract to Phillips Hardy, Inc. to complete the bridge rehabilitation project.

The earliest date the contractor could begin work is July 10, 2023. 

 

milestone_icon
Not Started
Construction Schedule

The contractor will work with MoDOT to determine the exact schedule of work.

At this time, the roadway is expected to close during construction. The exact date of the road closure and the planned reopening date has not been determined yet. 

milestone_icon
Not Started
Contract Completion

By contract, all work must be complete on or before Oct. 1, 2024.

milestone_icon

Project News

Webform
Sign up for email updates:
*
*
*