Bike/Pedestrian and ADA Transition Plan Improvements - 5d

MoDOT has identified 46,107 barriers within its right of way needing repaired or constructed to meet the requirements of the Americans with Disabilities Act.  A transition plan was established to correct these barriers by August 2027.

Embed
Is Responsive
Embed Code
Is Responsive
Embed Code

*Starting with FY19, ADA program data will be included in the measure

Write Up:

MoDOT has identified 46,107 barriers within its right of way needing to be repaired or constructed to meet the requirements of the Americans with Disabilities Act.  A transition plan was established to correct these barriers by August 2027. To meet the August 2027 transition plan deadline, a target of 78% was established for calendar year 2023. To date, MoDOT has completed 20,489 or 44% of the identified barriers.  

Since 2008, MoDOT has invested nearly $162.3 million towards the completion of the transition plan. The districts have projected to invest over $154 million towards the remainder of the ADA Transition Plan improvements in the Statewide Transportation Improvement Program. That amount is expected to cover transition plan improvements and other ADA needs across the state.

Purpose of the Measure:

This measure tracks MoDOT’s investment in non-motorized facilities and progress toward removing barriers. Accessibility needs occur within the right of way, such as sidewalks and traffic signals. Removal of the barriers listed in MoDOT’s 2010 ADA Transition Plan is required as part of the department’s compliance with the ADA.

Measurement and Data Collection:

MoDOT’s investment in non-motorized facilities is determined from the awarded contract amounts for the 20 most common construction elements used on projects each year. 

ADA Transition Plan progress is based upon completed work to correct deficient barriers identified in the ADA Transition Plan inventory.   

A progress target line is included indicating MoDOT’s progress towards completing the transition plan by 2027. Annual funding levels necessary to complete the transition plan by 2027 determine the target which is set in April of each year.

 

Results Driver

Mark Croarkin
Title
District Engineer
Department
Southeast District
Contact Info

Email: mark.croarkin@modot.mo.gov

Phone: (573) 472-5341

Measurement Driver

Contact Photo
amy photo
Amy Crawford
Title
Policy and Innovations Engineer
Department
Design
Contact Info

Email: amy.crawford@modot.mo.gov

Phone: (660) 651-1955